Course introduction · 3 min
MEP estimating: electrical and HVAC takeoff and bid (US)
Harwick Medical Office · Two-storey outpatient building, Texas · Fictional project
You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.
- Building
- Two-storey medical office, 24,000 sf
- Contract
- Lump-sum MEP subcontract to the general contractor (one fixed price)
- Story
- March to July 2026
- Work in the ERP
- 6 tasks, about 3 h 37 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- General contractorGeneral contractor
- Drawings and bid formTask 1
- Bulletin 2, answering RFI 14Task 6
- Controls and balancing firmsYour sub-subcontractors
- Quotes, tax already inTask 5
Goes from you
- MEP bidTask 5
- Change orderTask 6
- Labor hours they are budgetedTask 3
Your route through the job
Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.
Takeoff and pricing
Task 1 · 12 min
Electrical takeoff: count the devices
- You produce
- Device counts for the exam wing
- Document
- Level 1 electrical plan, exam wing
- In the ERP
- Bill of Quantities
Takeoff and pricing
Task 2 · 25 min
Electrical takeoff: conduit and wire for circuit A-7
- You produce
- Conduit and wire for one circuit
- Document
- Circuit A-7 runs and heights
- In the ERP
- Bill of Quantities
Takeoff and pricing
Task 3 · 45 min
Price the electrical with labor units
- You produce
- Electrical unit rates and the labor hours
- Document
- Labor units (hours per item) and the crew rate
- In the ERP
- Bill of Quantities
Takeoff and pricing
Task 4 · 45 min
Ductwork: weight by gauge
- You produce
- Supply trunk weight and its price
- Document
- Duct layout, trunk TR-1
- In the ERP
- Bill of Quantities
The bid
Task 5 · 50 min
Build the MEP bid: burden, tax, markups, bond
- You produce
- The bid price to the general contractor
- Document
- Bid terms, tax rule, quotes from sub-subcontractors
- In the ERP
- Bill of Quantities, Markups
After award
Task 6 · 40 min
Price the change order from RFI 14
- You produce
- The change order, approved and completed
- Document
- Bulletin 2 and the change terms
- In the ERP
- Variations
How a drawing becomes a bid
Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.
Blue is what the task adds; grey is carried over from before.
In short. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.