Course introduction · 3 min

MEP estimating: electrical and HVAC takeoff and bid (US)

Harwick Medical Office · Two-storey outpatient building, Texas · Fictional project

You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.

Start task 1

Building
Two-storey medical office, 24,000 sf
Contract
Lump-sum MEP subcontract to the general contractor (one fixed price)
Story
March to July 2026
Work in the ERP
6 tasks, about 3 h 37 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • General contractorGeneral contractor
    • Drawings and bid formTask 1
    • Bulletin 2, answering RFI 14Task 6
  • Controls and balancing firmsYour sub-subcontractors
    • Quotes, tax already inTask 5
YouEstimator, MEP subcontractor

Goes from you

    • MEP bidTask 5
    • Change orderTask 6
    General contractorReceives your price
    • Labor hours they are budgetedTask 3
    Your field crewsElectricians, sheet metal, pipefitters

Your route through the job

Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.

  1. Takeoff and pricing

    Task 1 · 12 min

    Electrical takeoff: count the devices

    You produce
    Device counts for the exam wing
    Document
    Level 1 electrical plan, exam wing
    In the ERP
    Bill of Quantities
  2. Takeoff and pricing

    Task 2 · 25 min

    Electrical takeoff: conduit and wire for circuit A-7

    You produce
    Conduit and wire for one circuit
    Document
    Circuit A-7 runs and heights
    In the ERP
    Bill of Quantities
  3. Takeoff and pricing

    Task 3 · 45 min

    Price the electrical with labor units

    You produce
    Electrical unit rates and the labor hours
    Document
    Labor units (hours per item) and the crew rate
    In the ERP
    Bill of Quantities
  4. Takeoff and pricing

    Task 4 · 45 min

    Ductwork: weight by gauge

    You produce
    Supply trunk weight and its price
    Document
    Duct layout, trunk TR-1
    In the ERP
    Bill of Quantities
  5. The bid

    Task 5 · 50 min

    Build the MEP bid: burden, tax, markups, bond

    You produce
    The bid price to the general contractor
    Document
    Bid terms, tax rule, quotes from sub-subcontractors
    In the ERP
    Bill of Quantities, Markups
  6. After award

    Task 6 · 40 min

    Price the change order from RFI 14

    You produce
    The change order, approved and completed
    Document
    Bulletin 2 and the change terms
    In the ERP
    Variations

How a drawing becomes a bid

Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.

Counts and lengths
Task 1QuantitiesCount devices (outlets, switches, lights), measure conduit, the pipe the wire runs in, with its rise and drops, then wire.
MaterialLabor at base wage
Task 3Direct costHours times crew rate, plus material, line by line.
Overhead, profit, bondBurden, tools, taxMaterialLabor
Task 5Bid priceBurden (payroll taxes and insurance), tools and tax as lines; overhead, profit and bond on top, in order.
Change orderBid price
Task 6Change orderAdds less deducts at bid rates, then the change terms once.

Blue is what the task adds; grey is carried over from before.

In short. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.