Panimula ng kurso · 3 min
MEP estimating: electrical at HVAC takeoff, pagpepresyo at ang bid (Estados Unidos)
Harwick Medical Office · Two-storey outpatient building, Texas · Kathang-isip na proyekto
You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.
- Building
- Two-storey medical office, 24,000 sf
- Contract
- Lump-sum MEP subcontract to the general contractor (one fixed price)
- Story
- March to July 2026
- Trabaho sa ERP
- 6 gawain, mga 3 oras 37 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- General contractorGeneral contractor
- Drawings and bid formGawain 1
- Bulletin 2, answering RFI 14Gawain 6
- Controls and balancing firmsYour sub-subcontractors
- Quotes, tax already inGawain 5
Lumalabas sa iyo
- MEP bidGawain 5
- Change orderGawain 6
- Labor hours they are budgetedGawain 3
Ang ruta mo sa proyekto
Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.
Takeoff and pricing
Gawain 1 · 12 min
Electrical takeoff: bilangin ang mga device
- Ang gagawin mo
- Device counts for the exam wing
- Dokumento
- Level 1 electrical plan, exam wing
- Sa ERP
- Bill of Quantities
Takeoff and pricing
Gawain 2 · 25 min
Electrical takeoff: conduit at wire para sa circuit A-7
- Ang gagawin mo
- Conduit and wire for one circuit
- Dokumento
- Circuit A-7 runs and heights
- Sa ERP
- Bill of Quantities
Takeoff and pricing
Gawain 3 · 45 min
Presyuhan ang electrical gamit ang mga labor unit
- Ang gagawin mo
- Electrical unit rates and the labor hours
- Dokumento
- Labor units (hours per item) and the crew rate
- Sa ERP
- Bill of Quantities
Takeoff and pricing
Gawain 4 · 45 min
Ductwork: bigat ayon sa gauge
- Ang gagawin mo
- Supply trunk weight and its price
- Dokumento
- Duct layout, trunk TR-1
- Sa ERP
- Bill of Quantities
The bid
Gawain 5 · 50 min
Buuin ang MEP bid: burden, buwis, markup, bond
- Ang gagawin mo
- The bid price to the general contractor
- Dokumento
- Bid terms, tax rule, quotes from sub-subcontractors
- Sa ERP
- Bill of Quantities, Markups
After award
Gawain 6 · 40 min
Presyuhan ang change order mula sa RFI 14
- Ang gagawin mo
- The change order, approved and completed
- Dokumento
- Bulletin 2 and the change terms
- Sa ERP
- Variations
How a drawing becomes a bid
Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.