Inleiding tot de cursus · 3 min
MEP-calculatie: elektrotechnische en HVAC-uittrekstaat, prijsberekening en de inschrijving (VS)
Harwick Medical Office · Two-storey outpatient building, Texas · Fictief project
You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.
- Building
- Two-storey medical office, 24,000 sf
- Contract
- Lump-sum MEP subcontract to the general contractor (one fixed price)
- Story
- March to July 2026
- Werk in de ERP
- 6 opdrachten, ongeveer 3 u 37 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- General contractorGeneral contractor
- Drawings and bid formOpdracht 1
- Bulletin 2, answering RFI 14Opdracht 6
- Controls and balancing firmsYour sub-subcontractors
- Quotes, tax already inOpdracht 5
Gaat van u uit
- MEP bidOpdracht 5
- Change orderOpdracht 6
- Labor hours they are budgetedOpdracht 3
Uw route door het project
Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.
Takeoff and pricing
Opdracht 1 · 12 min
Elektro-opname: tel de voorzieningen
- U levert
- Device counts for the exam wing
- Document
- Level 1 electrical plan, exam wing
- In de ERP
- Bill of Quantities
Takeoff and pricing
Opdracht 2 · 25 min
Elektro-opname: buis en draad voor groep A-7
- U levert
- Conduit and wire for one circuit
- Document
- Circuit A-7 runs and heights
- In de ERP
- Bill of Quantities
Takeoff and pricing
Opdracht 3 · 45 min
Prijs het elektrawerk met normuren
- U levert
- Electrical unit rates and the labor hours
- Document
- Labor units (hours per item) and the crew rate
- In de ERP
- Bill of Quantities
Takeoff and pricing
Opdracht 4 · 45 min
Luchtkanalen: gewicht per gauge
- U levert
- Supply trunk weight and its price
- Document
- Duct layout, trunk TR-1
- In de ERP
- Bill of Quantities
The bid
Opdracht 5 · 50 min
Stel de MEP-offerte samen: loonlasten, belasting, opslagen, borgstelling
- U levert
- The bid price to the general contractor
- Document
- Bid terms, tax rule, quotes from sub-subcontractors
- In de ERP
- Bill of Quantities, Markups
After award
Opdracht 6 · 40 min
Prijs de wijzigingsopdracht van RFI 14
- U levert
- The change order, approved and completed
- Document
- Bulletin 2 and the change terms
- In de ERP
- Variations
How a drawing becomes a bid
Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.