Inleiding tot de cursus · 3 min

MEP-calculatie: elektrotechnische en HVAC-uittrekstaat, prijsberekening en de inschrijving (VS)

Harwick Medical Office · Two-storey outpatient building, Texas · Fictief project

You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.

Start opdracht 1

Building
Two-storey medical office, 24,000 sf
Contract
Lump-sum MEP subcontract to the general contractor (one fixed price)
Story
March to July 2026
Werk in de ERP
6 opdrachten, ongeveer 3 u 37 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • General contractorGeneral contractor
    • Drawings and bid formOpdracht 1
    • Bulletin 2, answering RFI 14Opdracht 6
  • Controls and balancing firmsYour sub-subcontractors
    • Quotes, tax already inOpdracht 5
UEstimator, MEP subcontractor

Gaat van u uit

    • MEP bidOpdracht 5
    • Change orderOpdracht 6
    General contractorReceives your price
    • Labor hours they are budgetedOpdracht 3
    Your field crewsElectricians, sheet metal, pipefitters

Uw route door het project

Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.

  1. Takeoff and pricing

    Opdracht 1 · 12 min

    Elektro-opname: tel de voorzieningen

    U levert
    Device counts for the exam wing
    Document
    Level 1 electrical plan, exam wing
    In de ERP
    Bill of Quantities
  2. Takeoff and pricing

    Opdracht 2 · 25 min

    Elektro-opname: buis en draad voor groep A-7

    U levert
    Conduit and wire for one circuit
    Document
    Circuit A-7 runs and heights
    In de ERP
    Bill of Quantities
  3. Takeoff and pricing

    Opdracht 3 · 45 min

    Prijs het elektrawerk met normuren

    U levert
    Electrical unit rates and the labor hours
    Document
    Labor units (hours per item) and the crew rate
    In de ERP
    Bill of Quantities
  4. Takeoff and pricing

    Opdracht 4 · 45 min

    Luchtkanalen: gewicht per gauge

    U levert
    Supply trunk weight and its price
    Document
    Duct layout, trunk TR-1
    In de ERP
    Bill of Quantities
  5. The bid

    Opdracht 5 · 50 min

    Stel de MEP-offerte samen: loonlasten, belasting, opslagen, borgstelling

    U levert
    The bid price to the general contractor
    Document
    Bid terms, tax rule, quotes from sub-subcontractors
    In de ERP
    Bill of Quantities, Markups
  6. After award

    Opdracht 6 · 40 min

    Prijs de wijzigingsopdracht van RFI 14

    U levert
    The change order, approved and completed
    Document
    Bulletin 2 and the change terms
    In de ERP
    Variations

How a drawing becomes a bid

Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.

Counts and lengths
Opdracht 1QuantitiesCount devices (outlets, switches, lights), measure conduit, the pipe the wire runs in, with its rise and drops, then wire.
MaterialLabor at base wage
Opdracht 3Direct costHours times crew rate, plus material, line by line.
Overhead, profit, bondBurden, tools, taxMaterialLabor
Opdracht 5Bid priceBurden (payroll taxes and insurance), tools and tax as lines; overhead, profit and bond on top, in order.
Change orderBid price
Opdracht 6Change orderAdds less deducts at bid rates, then the change terms once.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.