Uvod u tečaj · 3 min
MEP predračun: iskaz količina elektro i HVAC instalacija, cijene i ponuda (SAD)
Harwick Medical Office · Two-storey outpatient building, Texas · Izmišljeni projekt
You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.
- Building
- Two-storey medical office, 24,000 sf
- Contract
- Lump-sum MEP subcontract to the general contractor (one fixed price)
- Story
- March to July 2026
- Rad u ERP-u
- Zadataka: 6, oko 3 h 37 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- General contractorGeneral contractor
- Drawings and bid formZadatak 1
- Bulletin 2, answering RFI 14Zadatak 6
- Controls and balancing firmsYour sub-subcontractors
- Quotes, tax already inZadatak 5
Odlazi od vas
- MEP bidZadatak 5
- Change orderZadatak 6
- Labor hours they are budgetedZadatak 3
Vaš put kroz projekt
Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.
Takeoff and pricing
Zadatak 1 · 12 min
Elektro iskaz količina: brojanje uređaja
- Vaš rezultat
- Device counts for the exam wing
- Dokument
- Level 1 electrical plan, exam wing
- U ERP-u
- Bill of Quantities
Takeoff and pricing
Zadatak 2 · 25 min
Elektro iskaz količina: cijev i vodič za strujni krug A-7
- Vaš rezultat
- Conduit and wire for one circuit
- Dokument
- Circuit A-7 runs and heights
- U ERP-u
- Bill of Quantities
Takeoff and pricing
Zadatak 3 · 45 min
Odredite cijenu elektroinstalacija s normama rada
- Vaš rezultat
- Electrical unit rates and the labor hours
- Dokument
- Labor units (hours per item) and the crew rate
- U ERP-u
- Bill of Quantities
Takeoff and pricing
Zadatak 4 · 45 min
Zračni kanali: težina po debljini lima
- Vaš rezultat
- Supply trunk weight and its price
- Dokument
- Duct layout, trunk TR-1
- U ERP-u
- Bill of Quantities
The bid
Zadatak 5 · 50 min
Sastavite MEP ponudu: doprinosi, porez, doplaci, jamstvo
- Vaš rezultat
- The bid price to the general contractor
- Dokument
- Bid terms, tax rule, quotes from sub-subcontractors
- U ERP-u
- Bill of Quantities, Markups
After award
Zadatak 6 · 40 min
Odredite cijenu izmjene ugovora prema RFI 14
- Vaš rezultat
- The change order, approved and completed
- Dokument
- Bulletin 2 and the change terms
- U ERP-u
- Variations
How a drawing becomes a bid
Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.