El- og VVS-kalkulation: opmåling af el og ventilation, prissætning og tilbud (USA)

Harwick Medical Office · Two-storey outpatient building, Texas · Fiktivt projekt

You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.

Start opgave 1

Building
Two-storey medical office, 24,000 sf
Contract
Lump-sum MEP subcontract to the general contractor (one fixed price)
Story
March to July 2026
Arbejde i ERP
6 opgaver, cirka 3 t 37 min

Hvem giver hvad til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til dig

  • General contractorGeneral contractor
    • Drawings and bid formOpgave 1
    • Bulletin 2, answering RFI 14Opgave 6
  • Controls and balancing firmsYour sub-subcontractors
    • Quotes, tax already inOpgave 5
DigEstimator, MEP subcontractor

Går fra dig

    • MEP bidOpgave 5
    • Change orderOpgave 6
    General contractorReceives your price
    • Labor hours they are budgetedOpgave 3
    Your field crewsElectricians, sheet metal, pipefitters

Din vej gennem sagen

Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.

  1. Takeoff and pricing

    Opgave 1 · 12 min

    Opmåling af el: tæl enhederne

    Du leverer
    Device counts for the exam wing
    Dokument
    Level 1 electrical plan, exam wing
    I ERP
    Bill of Quantities
  2. Takeoff and pricing

    Opgave 2 · 25 min

    Opmåling af el: rør og ledning til kredsløb A-7

    Du leverer
    Conduit and wire for one circuit
    Dokument
    Circuit A-7 runs and heights
    I ERP
    Bill of Quantities
  3. Takeoff and pricing

    Opgave 3 · 45 min

    Prissæt elarbejdet med arbejdsnormer

    Du leverer
    Electrical unit rates and the labor hours
    Dokument
    Labor units (hours per item) and the crew rate
    I ERP
    Bill of Quantities
  4. Takeoff and pricing

    Opgave 4 · 45 min

    Ventilationskanaler: vægt efter pladetykkelse

    Du leverer
    Supply trunk weight and its price
    Dokument
    Duct layout, trunk TR-1
    I ERP
    Bill of Quantities
  5. The bid

    Opgave 5 · 50 min

    Byg MEP-tilbuddet: sociale omkostninger, afgift, tillæg, garanti

    Du leverer
    The bid price to the general contractor
    Dokument
    Bid terms, tax rule, quotes from sub-subcontractors
    I ERP
    Bill of Quantities, Markups
  6. After award

    Opgave 6 · 40 min

    Prissæt tillægsarbejdet fra RFI 14

    Du leverer
    The change order, approved and completed
    Dokument
    Bulletin 2 and the change terms
    I ERP
    Variations

How a drawing becomes a bid

Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.

Counts and lengths
Opgave 1QuantitiesCount devices (outlets, switches, lights), measure conduit, the pipe the wire runs in, with its rise and drops, then wire.
MaterialLabor at base wage
Opgave 3Direct costHours times crew rate, plus material, line by line.
Overhead, profit, bondBurden, tools, taxMaterialLabor
Opgave 5Bid priceBurden (payroll taxes and insurance), tools and tax as lines; overhead, profit and bond on top, in order.
Change orderBid price
Opgave 6Change orderAdds less deducts at bid rates, then the change terms once.

Blå er det, opgaven tilføjer; grå er overført fra før.

Kort sagt. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.