MEP-kalkylering: elektrisk och VVS-mängdavtagning, prissättning och anbudet (USA)
Harwick Medical Office · Two-storey outpatient building, Texas · Fiktivt projekt
You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.
- Building
- Two-storey medical office, 24,000 sf
- Contract
- Lump-sum MEP subcontract to the general contractor (one fixed price)
- Story
- March to July 2026
- Arbete i ERP
- 6 uppgifter, cirka 3 h 37 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- General contractorGeneral contractor
- Drawings and bid formUppgift 1
- Bulletin 2, answering RFI 14Uppgift 6
- Controls and balancing firmsYour sub-subcontractors
- Quotes, tax already inUppgift 5
Går från dig
- MEP bidUppgift 5
- Change orderUppgift 6
- Labor hours they are budgetedUppgift 3
Din väg genom projektet
Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.
Takeoff and pricing
Uppgift 1 · 12 min
Elmängdning: räkna apparaterna
- Du tar fram
- Device counts for the exam wing
- Dokument
- Level 1 electrical plan, exam wing
- I ERP
- Bill of Quantities
Takeoff and pricing
Uppgift 2 · 25 min
Elmängdning: rör och ledning för krets A-7
- Du tar fram
- Conduit and wire for one circuit
- Dokument
- Circuit A-7 runs and heights
- I ERP
- Bill of Quantities
Takeoff and pricing
Uppgift 3 · 45 min
Prissätt elen med arbetstidsnormer
- Du tar fram
- Electrical unit rates and the labor hours
- Dokument
- Labor units (hours per item) and the crew rate
- I ERP
- Bill of Quantities
Takeoff and pricing
Uppgift 4 · 45 min
Ventilationskanaler: vikt efter plåttjocklek
- Du tar fram
- Supply trunk weight and its price
- Dokument
- Duct layout, trunk TR-1
- I ERP
- Bill of Quantities
The bid
Uppgift 5 · 50 min
Bygg MEP-anbudet: lönebikostnader, skatt, påslag, borgen
- Du tar fram
- The bid price to the general contractor
- Dokument
- Bid terms, tax rule, quotes from sub-subcontractors
- I ERP
- Bill of Quantities, Markups
After award
Uppgift 6 · 40 min
Prissätt ändringsordern utifrån RFI 14
- Du tar fram
- The change order, approved and completed
- Dokument
- Bulletin 2 and the change terms
- I ERP
- Variations
How a drawing becomes a bid
Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.