MEP-hindamine: elektri- ja ventilatsioonitööde mahuvõtt, hinnastamine ja pakkumine (USA)

Harwick Medical Office · Two-storey outpatient building, Texas · Väljamõeldud projekt

You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.

Alusta ülesannet 1

Building
Two-storey medical office, 24,000 sf
Contract
Lump-sum MEP subcontract to the general contractor (one fixed price)
Story
March to July 2026
Töö ERP-s
Ülesandeid 6, umbes 3 h 37 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • General contractorGeneral contractor
    • Drawings and bid formÜlesanne 1
    • Bulletin 2, answering RFI 14Ülesanne 6
  • Controls and balancing firmsYour sub-subcontractors
    • Quotes, tax already inÜlesanne 5
SinaEstimator, MEP subcontractor

Läheb sinult

    • MEP bidÜlesanne 5
    • Change orderÜlesanne 6
    General contractorReceives your price
    • Labor hours they are budgetedÜlesanne 3
    Your field crewsElectricians, sheet metal, pipefitters

Sinu tee läbi projekti

Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.

  1. Takeoff and pricing

    Ülesanne 1 · 12 min

    Elektritööde mahud: seadmete loendus

    Sinu tulemus
    Device counts for the exam wing
    Dokument
    Level 1 electrical plan, exam wing
    ERP-s
    Bill of Quantities
  2. Takeoff and pricing

    Ülesanne 2 · 25 min

    Elektritööde mahud: kaitsetoru ja juhe vooluringile A-7

    Sinu tulemus
    Conduit and wire for one circuit
    Dokument
    Circuit A-7 runs and heights
    ERP-s
    Bill of Quantities
  3. Takeoff and pricing

    Ülesanne 3 · 45 min

    Elektritööde hinnastamine tööjõunormidega

    Sinu tulemus
    Electrical unit rates and the labor hours
    Dokument
    Labor units (hours per item) and the crew rate
    ERP-s
    Bill of Quantities
  4. Takeoff and pricing

    Ülesanne 4 · 45 min

    Ventilatsioonikanalid: kaal plekipaksuse järgi

    Sinu tulemus
    Supply trunk weight and its price
    Dokument
    Duct layout, trunk TR-1
    ERP-s
    Bill of Quantities
  5. The bid

    Ülesanne 5 · 50 min

    MEP-pakkumise koostamine: lisakulu, maks, juurdehindlused, tagatis

    Sinu tulemus
    The bid price to the general contractor
    Dokument
    Bid terms, tax rule, quotes from sub-subcontractors
    ERP-s
    Bill of Quantities, Markups
  6. After award

    Ülesanne 6 · 40 min

    Muudatustellimuse hinnastamine RFI 14 põhjal

    Sinu tulemus
    The change order, approved and completed
    Dokument
    Bulletin 2 and the change terms
    ERP-s
    Variations

How a drawing becomes a bid

Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.

Counts and lengths
Ülesanne 1QuantitiesCount devices (outlets, switches, lights), measure conduit, the pipe the wire runs in, with its rise and drops, then wire.
MaterialLabor at base wage
Ülesanne 3Direct costHours times crew rate, plus material, line by line.
Overhead, profit, bondBurden, tools, taxMaterialLabor
Ülesanne 5Bid priceBurden (payroll taxes and insurance), tools and tax as lines; overhead, profit and bond on top, in order.
Change orderBid price
Ülesanne 6Change orderAdds less deducts at bid rates, then the change terms once.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.