Kursuse sissejuhatus · 3 min
MEP-hindamine: elektri- ja ventilatsioonitööde mahuvõtt, hinnastamine ja pakkumine (USA)
Harwick Medical Office · Two-storey outpatient building, Texas · Väljamõeldud projekt
You are the estimator at the mechanical, electrical and plumbing (MEP) subcontractor, the firm that installs the building's services: you work out what the job will cost and what to bid. In six tasks you take a medical office in Texas from the drawings to a lump-sum bid, one fixed price for the whole MEP package, to the general contractor (GC), then price the first change order after the award.
- Building
- Two-storey medical office, 24,000 sf
- Contract
- Lump-sum MEP subcontract to the general contractor (one fixed price)
- Story
- March to July 2026
- Töö ERP-s
- Ülesandeid 6, umbes 3 h 37 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- General contractorGeneral contractor
- Drawings and bid formÜlesanne 1
- Bulletin 2, answering RFI 14Ülesanne 6
- Controls and balancing firmsYour sub-subcontractors
- Quotes, tax already inÜlesanne 5
Läheb sinult
- MEP bidÜlesanne 5
- Change orderÜlesanne 6
- Labor hours they are budgetedÜlesanne 3
Sinu tee läbi projekti
Four tasks turn drawings into quantities and direct cost, one builds the bid, one prices a change after the award. Start with task 1: in the Bill of Quantities you count the devices on the Level 1 electrical plan; task 2 measures conduit and wire for one circuit.
Takeoff and pricing
Ülesanne 1 · 12 min
Elektritööde mahud: seadmete loendus
- Sinu tulemus
- Device counts for the exam wing
- Dokument
- Level 1 electrical plan, exam wing
- ERP-s
- Bill of Quantities
Takeoff and pricing
Ülesanne 2 · 25 min
Elektritööde mahud: kaitsetoru ja juhe vooluringile A-7
- Sinu tulemus
- Conduit and wire for one circuit
- Dokument
- Circuit A-7 runs and heights
- ERP-s
- Bill of Quantities
Takeoff and pricing
Ülesanne 3 · 45 min
Elektritööde hinnastamine tööjõunormidega
- Sinu tulemus
- Electrical unit rates and the labor hours
- Dokument
- Labor units (hours per item) and the crew rate
- ERP-s
- Bill of Quantities
Takeoff and pricing
Ülesanne 4 · 45 min
Ventilatsioonikanalid: kaal plekipaksuse järgi
- Sinu tulemus
- Supply trunk weight and its price
- Dokument
- Duct layout, trunk TR-1
- ERP-s
- Bill of Quantities
The bid
Ülesanne 5 · 50 min
MEP-pakkumise koostamine: lisakulu, maks, juurdehindlused, tagatis
- Sinu tulemus
- The bid price to the general contractor
- Dokument
- Bid terms, tax rule, quotes from sub-subcontractors
- ERP-s
- Bill of Quantities, Markups
After award
Ülesanne 6 · 40 min
Muudatustellimuse hinnastamine RFI 14 põhjal
- Sinu tulemus
- The change order, approved and completed
- Dokument
- Bulletin 2 and the change terms
- ERP-s
- Variations
How a drawing becomes a bid
Each step below is one task, in the order the money is built. Task 4 does for the ductwork what tasks 1 to 3 do for the electrical.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Hours are not dollars. Each layer has its own base. Net the change before you mark it up.