কাজ 5-এর আগে তত্ত্ব · 7 মি

Contract penalty after a hindrance: § 11 VOB/B

জরিমানার চিঠি

এই লেকচারের পর আপনি পারবেন

  1. Say when a penalty for a date is due.
  2. Move the date by the extensions and count delay.
  3. Check the reservation at acceptance and the cap.
1 / 3

No delay, no penalty

A penalty for missing a date is due only when the contractor is in delay (§ 339 BGB). Extensions of time move the date, so days inside the extended period are not delay. A client who counts from the original date counts days it caused itself.

উদাহরণ. Due 1 June, extended by 10 working days, finished 4 working days after the new date: 4 days of penalty.
Client's count
€14 (€10 + €4)
Delay
€4
2 / 3

Acceptance and the cap

After acceptance the client can claim the penalty only if it reserved it at acceptance (§ 11 (4)). In standard terms the total may not exceed 5 % of the contract sum; the cap is a ceiling, not the amount.

উদাহরণ. A deduction at the full cap for four days late is the cap misread as a price.
সাধারণ ভুল

Accepting the deduction

The deduction arrives with the payment and looks final. Check the reservation, move the date, count the days the contract counts, and answer in writing with the amount you accept.

উদাহরণ. Net sum €800,000, 0.2 % a day: each day is €1,600.00; four days are €6,400.00, not the €32,000.00 cap.

Penalty after an extension

Different numbers from your task.

মাপমতো নয়
সমস্যা
  • Net contract sum €800,000; 0.2 % per working day, at most 5 %.
  • 4 working days of delay after the extended date.
ধাপ 1 / 1

Penalty

What penalty is owed?

€800,000 × 0.2 % × 4 = €6,400.00.

সংক্ষেপে. Move the date, count the delay, apply the daily rate, check the cap.

নিজেকে যাচাই করুন

প্রশ্ন 1 / 3

The client did not reserve the penalty at acceptance. Penalty?

  • Right: § 11 (4).

  • There is no halving.

  • The reservation was needed at acceptance.

প্রশ্ন 2 / 3

What does the 5 % cap do?

  • Right.

  • It is a ceiling.

  • The daily rate is separate.

প্রশ্ন 3 / 3

Net sum €500,000, 0.2 % a day, 3 days late after the extended date. Penalty?

500,000 × 0.2 % × 3 = 3,000.