Θεωρία πριν από την εργασία 5 · 7 λ.

Contract penalty after a hindrance: § 11 VOB/B

Η επιστολή ποινικής ρήτρας

Μετά από αυτή τη διάλεξη μπορείτε να

  1. Say when a penalty for a date is due.
  2. Move the date by the extensions and count delay.
  3. Check the reservation at acceptance and the cap.
1 / 3

No delay, no penalty

A penalty for missing a date is due only when the contractor is in delay (§ 339 BGB). Extensions of time move the date, so days inside the extended period are not delay. A client who counts from the original date counts days it caused itself.

Παράδειγμα. Due 1 June, extended by 10 working days, finished 4 working days after the new date: 4 days of penalty.
Client's count
€14 (€10 + €4)
Delay
€4
2 / 3

Acceptance and the cap

After acceptance the client can claim the penalty only if it reserved it at acceptance (§ 11 (4)). In standard terms the total may not exceed 5 % of the contract sum; the cap is a ceiling, not the amount.

Παράδειγμα. A deduction at the full cap for four days late is the cap misread as a price.
Συνηθισμένο λάθος

Accepting the deduction

The deduction arrives with the payment and looks final. Check the reservation, move the date, count the days the contract counts, and answer in writing with the amount you accept.

Παράδειγμα. Net sum €800,000, 0.2 % a day: each day is €1,600.00; four days are €6,400.00, not the €32,000.00 cap.

Penalty after an extension

Different numbers from your task.

Όχι υπό κλίμακα
Το πρόβλημα
  • Net contract sum €800,000; 0.2 % per working day, at most 5 %.
  • 4 working days of delay after the extended date.
Βήμα 1 από 1

Penalty

What penalty is owed?

€800,000 × 0.2 % × 4 = €6,400.00.

Με λίγα λόγια. Move the date, count the delay, apply the daily rate, check the cap.

Ελέγξτε τον εαυτό σας

Ερώτηση 1 από 3

The client did not reserve the penalty at acceptance. Penalty?

  • Right: § 11 (4).

  • There is no halving.

  • The reservation was needed at acceptance.

Ερώτηση 2 από 3

What does the 5 % cap do?

  • Right.

  • It is a ceiling.

  • The daily rate is separate.

Ερώτηση 3 από 3

Net sum €500,000, 0.2 % a day, 3 days late after the extended date. Penalty?

500,000 × 0.2 % × 3 = 3,000.

Πηγές

Δωρεάν επίσημα κείμενα. Η διάλεξη αναφέρει αριθμούς άρθρων και αποδίδει τους κανόνες με δικά της λόγια.