Contract penalty after a hindrance: § 11 VOB/B

Dopis o smluvní pokutě

Po této přednášce dokážete

  1. Say when a penalty for a date is due.
  2. Move the date by the extensions and count delay.
  3. Check the reservation at acceptance and the cap.
1 / 3

No delay, no penalty

A penalty for missing a date is due only when the contractor is in delay (§ 339 BGB). Extensions of time move the date, so days inside the extended period are not delay. A client who counts from the original date counts days it caused itself.

Příklad. Due 1 June, extended by 10 working days, finished 4 working days after the new date: 4 days of penalty.
Client's count
€14 (€10 + €4)
Delay
€4
2 / 3

Acceptance and the cap

After acceptance the client can claim the penalty only if it reserved it at acceptance (§ 11 (4)). In standard terms the total may not exceed 5 % of the contract sum; the cap is a ceiling, not the amount.

Příklad. A deduction at the full cap for four days late is the cap misread as a price.
Častá chyba

Accepting the deduction

The deduction arrives with the payment and looks final. Check the reservation, move the date, count the days the contract counts, and answer in writing with the amount you accept.

Příklad. Net sum €800,000, 0.2 % a day: each day is €1,600.00; four days are €6,400.00, not the €32,000.00 cap.

Penalty after an extension

Different numbers from your task.

Není v měřítku
Zadání
  • Net contract sum €800,000; 0.2 % per working day, at most 5 %.
  • 4 working days of delay after the extended date.
Krok 1 z 1

Penalty

What penalty is owed?

€800,000 × 0.2 % × 4 = €6,400.00.

Stručně. Move the date, count the delay, apply the daily rate, check the cap.

Zkontrolujte se

Otázka 1 z 3

The client did not reserve the penalty at acceptance. Penalty?

  • Right: § 11 (4).

  • There is no halving.

  • The reservation was needed at acceptance.

Otázka 2 z 3

What does the 5 % cap do?

  • Right.

  • It is a ceiling.

  • The daily rate is separate.

Otázka 3 z 3

Net sum €500,000, 0.2 % a day, 3 days late after the extended date. Penalty?

500,000 × 0.2 % × 3 = 3,000.

Zdroje

Bezplatné oficiální texty. Lekce uvádí čísla ustanovení a pravidla popisuje vlastními slovy.