Cheat sheet
AI-priced estimates: check the rates before you bid
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- A citation is not a source. The code must exist, be the current edition and be the row the item needs.
- How it is built
- Sound line = Code exists + Current edition + Right row for the item
- Shortfall = Corrected section 01 total − Draft section 01 total
- Usual mistake
- Counting every line that shows a citation. One of those codes is not in the library.
- At work
- Estimators look up every cited code in the firm's rate library before an AI-priced bill is used in a tender.
- Rule
- An existing row can still be the wrong row. Read the basis: what is included, what it is per.
- How it is built
- Line error = Quantity × (Right rate − draft rate)
- Largest error = Biggest line error in section 02
- Usual mistake
- That is the ex-works material price from the quotation.
- At work
- Every supplier quote is read for what it includes, delivered or erected, before its rate goes into a bill.
- Rule
- Rates are net. Overheads and profit are charged once, in the markup stack below the bill.
- How it is built
- Yard slab rate = Concrete with waste + Fabric with laps + Labour + Plant
- Outlet rate = Outlet set + Fitting labour
- Usual mistake
- That is the assistant's figure, with 25 % for overheads and profit inside it.
- At work
- When the library has no row, the estimator builds the rate from materials, labour and plant, and keeps it net.
- Rule
- Every markup row has a base. The percentage can be right and the amount still wrong.
- How it is built
- Preliminaries = Priced items of the schedule, added up
- Overheads = Overheads % × Direct cost
- Profit = Profit % × (Direct cost + Preliminaries + Overheads)
- Usual mistake
- That is 9 % of the direct cost, the assistant's benchmark. Use the schedule total.
- At work
- At the tender review the director checks each markup's base as closely as its percentage.
- Rule
- Order is part of the stack. A row above Profit is charged on by profit.
- How it is built
- Insurance and bonds = Its percentage × Direct cost
- Difference = (Verified sum − Draft sum) ÷ Verified sum
- Sum per m² = Verified sum ÷ Warehouse floor area
- Usual mistake
- The insurance row sits below profit, so profit did not charge on it. Move it above.
- At work
- Before signing, the estimator tests the tender sum per m² against similar buildings the firm has priced.