Cheat sheet

AI-priced estimates: check the rates before you bid

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Provenance first: which of the assistant's rates has a source at all

Theory (9 min)
Rule
A citation is not a source. The code must exist, be the current edition and be the row the item needs.
How it is built
  • Sound line = Code exists + Current edition + Right row for the item
  • Shortfall = Corrected section 01 total − Draft section 01 total
Usual mistake
Counting every line that shows a citation. One of those codes is not in the library.
At work
Estimators look up every cited code in the firm's rate library before an AI-priced bill is used in a tender.

Task 2

Matching: a real rate for the wrong item

Theory (10 min)
Rule
An existing row can still be the wrong row. Read the basis: what is included, what it is per.
How it is built
  • Line error = Quantity × (Right rate − draft rate)
  • Largest error = Biggest line error in section 02
Usual mistake
That is the ex-works material price from the quotation.
At work
Every supplier quote is read for what it includes, delivered or erected, before its rate goes into a bill.

Task 3

Build-ups: the assistant's own estimate, and what it quietly includes

Theory (10 min)
Rule
Rates are net. Overheads and profit are charged once, in the markup stack below the bill.
How it is built
  • Yard slab rate = Concrete with waste + Fabric with laps + Labour + Plant
  • Outlet rate = Outlet set + Fitting labour
Usual mistake
That is the assistant's figure, with 25 % for overheads and profit inside it.
At work
When the library has no row, the estimator builds the rate from materials, labour and plant, and keeps it net.

Task 4

The markup stack: the right percentage on the wrong base

Theory (10 min)
Rule
Every markup row has a base. The percentage can be right and the amount still wrong.
How it is built
  • Preliminaries = Priced items of the schedule, added up
  • Overheads = Overheads % × Direct cost
  • Profit = Profit % × (Direct cost + Preliminaries + Overheads)
Usual mistake
That is 9 % of the direct cost, the assistant's benchmark. Use the schedule total.
At work
At the tender review the director checks each markup's base as closely as its percentage.

Task 5

The row that was never produced, and the sum you sign

Theory (9 min)
Rule
Order is part of the stack. A row above Profit is charged on by profit.
How it is built
  • Insurance and bonds = Its percentage × Direct cost
  • Difference = (Verified sum − Draft sum) ÷ Verified sum
  • Sum per m² = Verified sum ÷ Warehouse floor area
Usual mistake
The insurance row sits below profit, so profit did not charge on it. Move it above.
At work
Before signing, the estimator tests the tender sum per m² against similar buildings the firm has priced.