Cheat sheet

Hold points and non-conformance reports (UK)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

A pour past an unreleased hold point

Theory (8 min)
Rule
A hold point not released is a nonconformity. Record it as it stands; the survey decides the steel.
How it is built
  • Volume in doubt = Area with voids deducted × Thickness in m
Usual mistake
The gross area used. The stair void and riser hold no concrete; use the area with voids deducted.
At work
A quality manager records a missed hold point the same morning, before anyone signs the sheet after the event.

Task 2

NCR-001 and the cover survey

Theory (9 min)
Rule
Grade on evidence, measure against the limit. Nominal is the target; the specification's limit decides.
How it is built
  • Area below cover = Bays under 20 mm + their areas
Usual mistake
You judged against the 30 mm nominal. The acceptance limit is 20 mm, nominal less the tolerance.
At work
The NCR is raised from the failed inspection, graded by the quality plan and kept open until the fix is verified.

Task 3

Root cause, and what it does to the programme

Theory (9 min)
Rule
Fix the step, not the person. A root cause is a step in the process you can change before the next pour.
How it is built
  • Delay = Working days from 23 April to the new start
Usual mistake
Calendar days counted. The programme runs in working days.
At work
Root cause goes on the NCR with a preventive action; the planner takes the delay into the next programme update.

Task 4

The cost of putting it right

Theory (8 min)
Rule
A Defect's cost includes its time. Price the delay to the critical path, not just the repair.
How it is built
  • NCR-001 cost = Survey + Engineer + Repair + Towers + Delay
Usual mistake
The standing time is missing. Six working days of site overheads are part of the cost.
At work
The NCR cost feeds the monthly cost report; repeated NCR costs are how a firm sees its cost of poor quality.

Task 5

Re-inspect, pay for the repeat test, close NCR-001

Theory (7 min)
Rule
Close the process, not only the product. The NCR closes when the fix is verified and the next pour has its gate.
How it is built
  • Paid to the Client = Supervisor's time + Client's specialist
Usual mistake
Your own specialist included. 41.6 covers the Client's cost only.
At work
The quality manager closes an NCR only after the re-inspection passes and the preventive action is in the next ITP.