Hold points and non-conformance reports (UK)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- A hold point not released is a nonconformity. Record it as it stands; the survey decides the steel.
- How it is built
- Volume in doubt = Area with voids deducted × Thickness in m
- Usual mistake
- The gross area used. The stair void and riser hold no concrete; use the area with voids deducted.
- At work
- A quality manager records a missed hold point the same morning, before anyone signs the sheet after the event.
- Rule
- Grade on evidence, measure against the limit. Nominal is the target; the specification's limit decides.
- How it is built
- Area below cover = Bays under 20 mm + their areas
- Usual mistake
- You judged against the 30 mm nominal. The acceptance limit is 20 mm, nominal less the tolerance.
- At work
- The NCR is raised from the failed inspection, graded by the quality plan and kept open until the fix is verified.
- Rule
- Fix the step, not the person. A root cause is a step in the process you can change before the next pour.
- How it is built
- Delay = Working days from 23 April to the new start
- Usual mistake
- Calendar days counted. The programme runs in working days.
- At work
- Root cause goes on the NCR with a preventive action; the planner takes the delay into the next programme update.
- Rule
- A Defect's cost includes its time. Price the delay to the critical path, not just the repair.
- How it is built
- NCR-001 cost = Survey + Engineer + Repair + Towers + Delay
- Usual mistake
- The standing time is missing. Six working days of site overheads are part of the cost.
- At work
- The NCR cost feeds the monthly cost report; repeated NCR costs are how a firm sees its cost of poor quality.
- Rule
- Close the process, not only the product. The NCR closes when the fix is verified and the next pour has its gate.
- How it is built
- Paid to the Client = Supervisor's time + Client's specialist
- Usual mistake
- Your own specialist included. 41.6 covers the Client's cost only.
- At work
- The quality manager closes an NCR only after the re-inspection passes and the preventive action is in the next ITP.