Earned value: is the GMP still safe? (US)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

The budget the lender measures you against

Theory (8 min)
Rule
The baseline holds authorized work only. Reserve and fee are in the GMP, not in the budget you earn against.
How it is built
  • Budget at completion = Cost of the work + Approved change cost
Usual mistake
That is the whole GMP. The fee is not a cost of work and the contingency is reserve, so neither is in the baseline.
At work
Project controls sets the baseline from the approved budget and changes it only through change control.

Task 2

What the October work was worth

Theory (9 min)
Rule
Earned value is a budget. Budget of the work done, account by account; never its cost, never the plan.
How it is built
  • Earned value = Σ budget × % complete + General conditions as planned
Usual mistake
Percent complete was applied to planned value. It is a share of the account's whole budget.
At work
Each month the super's progress walk is priced at budget, account by account, before any cost is looked at.

Task 3

Actual cost is not what accounting booked

Theory (8 min)
Rule
Cost and earned value cover the same work. Accrue what was done; leave out what bought no work yet.
How it is built
  • Actual cost = Booked − Deposit + Drywall accrual + Concrete accrual
Usual mistake
That is accounting's figure as booked. Take the deposit out and accrue the October work.
At work
Controls and accounting agree the accrual list at month end, so cost and earned value cover the same work.

Task 4

The outturn, and whether the contingency covers it

Theory (9 min)
Rule
Forecast from what the job has done, not what it hopes. The contingency absorbs the first part of an overrun; the rest is the CM's.
How it is built
  • Overrun of the GMP = Outturn (EAC) − Budget at completion − Contingency
Usual mistake
That is the whole variance at completion. The contingency absorbs the first part.
At work
The monthly report gives the outturn by the agreed method and the range, with the TCPI as a reality check.

Task 5

Rev 2: what may move into the baseline

Theory (8 min)
Rule
Change the future, never the past. Approved and newly found work joins the baseline; an overrun stays visible.
How it is built
  • Contingency left = Contingency − Firestopping
Usual mistake
The executive's transfer was taken from contingency. Refuse it: it would hide CA-40's overrun.
At work
Every baseline change goes through a change log with its source of funds: owner change, contingency, or refused.