Cheat sheet
Earned value: is the GMP still safe? (US)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- The baseline holds authorized work only. Reserve and fee are in the GMP, not in the budget you earn against.
- How it is built
- Budget at completion = Cost of the work + Approved change cost
- Usual mistake
- That is the whole GMP. The fee is not a cost of work and the contingency is reserve, so neither is in the baseline.
- At work
- Project controls sets the baseline from the approved budget and changes it only through change control.
- Rule
- Earned value is a budget. Budget of the work done, account by account; never its cost, never the plan.
- How it is built
- Earned value = Σ budget × % complete + General conditions as planned
- Usual mistake
- Percent complete was applied to planned value. It is a share of the account's whole budget.
- At work
- Each month the super's progress walk is priced at budget, account by account, before any cost is looked at.
- Rule
- Cost and earned value cover the same work. Accrue what was done; leave out what bought no work yet.
- How it is built
- Actual cost = Booked − Deposit + Drywall accrual + Concrete accrual
- Usual mistake
- That is accounting's figure as booked. Take the deposit out and accrue the October work.
- At work
- Controls and accounting agree the accrual list at month end, so cost and earned value cover the same work.
- Rule
- Forecast from what the job has done, not what it hopes. The contingency absorbs the first part of an overrun; the rest is the CM's.
- How it is built
- Overrun of the GMP = Outturn (EAC) − Budget at completion − Contingency
- Usual mistake
- That is the whole variance at completion. The contingency absorbs the first part.
- At work
- The monthly report gives the outturn by the agreed method and the range, with the TCPI as a reality check.
- Rule
- Change the future, never the past. Approved and newly found work joins the baseline; an overrun stays visible.
- How it is built
- Contingency left = Contingency − Firestopping
- Usual mistake
- The executive's transfer was taken from contingency. Refuse it: it would hide CA-40's overrun.
- At work
- Every baseline change goes through a change log with its source of funds: owner change, contingency, or refused.