Cheat sheet
Tender estimate: from net rates to the tender sum
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- A quote goes in as it stands. It is your net cost; overheads, risk and profit come once, at the end.
- How it is built
- Envelope = ENV.01 line + ENV.02 line
- Usual mistake
- The rates carry the mark-ups. A quote goes into the bill net; overheads, risk and profit are added once, in task 5.
- At work
- The estimator enters each subcontract quote at its quoted rate and keeps the company's margin for the summary.
- Rule
- Rates in the bill stay net. An all-in rate loses its mark-ups by division, one factor at a time.
- How it is built
- Net rate = All-in rate ÷ 1.06 ÷ 1.025 ÷ 1.05
- Measured work, net = Direct Cost
- Usual mistake
- That is the all-in rate. Its mark-ups would be charged again in task 5; take them out first.
- At work
- Rates from a cost database are stored all-in or net; the estimator checks which before using one.
- Rule
- The site costs money every month it runs. Months of the Time for Completion, plus what is paid once.
- How it is built
- Preliminaries = Fixed + Months × Monthly cost
- Usual mistake
- You priced 78 weeks at the monthly rate. The rate is per month: turn days into months.
- At work
- The estimator reads the period from the programme and prices the site per month, plus what is paid once.
- Rule
- A provisional sum is the client's figure. Enter it as stated; the Engineer decides how it is spent.
- How it is built
- Net cost = Direct Cost
- Usual mistake
- PS.01 carries the MEP offer. A provisional sum is entered as stated; the offer is not instructed work.
- At work
- The estimator copies each provisional sum from the tender documents and files any offer for after award.
- Rule
- Mark-ups go on once, at the end. Each on the running total, over the whole net cost.
- How it is built
- Tender sum = Grand Total
- Usual mistake
- The mark-ups sit on Sum of positions. Set each base to Running total incl. rows above.
- At work
- The estimating manager sets the mark-ups at the tender review, on the net cost the estimator presents.