Cheat sheet

Tender estimate: from net rates to the tender sum

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

A subcontract quote goes into the bill as a net rate

Theory (6 min)
Rule
A quote goes in as it stands. It is your net cost; overheads, risk and profit come once, at the end.
How it is built
  • Envelope = ENV.01 line + ENV.02 line
Usual mistake
The rates carry the mark-ups. A quote goes into the bill net; overheads, risk and profit are added once, in task 5.
At work
The estimator enters each subcontract quote at its quoted rate and keeps the company's margin for the summary.

Task 2

Rates stay net: take the mark-ups out of an all-in rate

Theory (7 min)
Rule
Rates in the bill stay net. An all-in rate loses its mark-ups by division, one factor at a time.
How it is built
  • Net rate = All-in rate ÷ 1.06 ÷ 1.025 ÷ 1.05
  • Measured work, net = Direct Cost
Usual mistake
That is the all-in rate. Its mark-ups would be charged again in task 5; take them out first.
At work
Rates from a cost database are stored all-in or net; the estimator checks which before using one.

Task 3

Preliminaries: what the site costs for as long as it runs

Theory (7 min)
Rule
The site costs money every month it runs. Months of the Time for Completion, plus what is paid once.
How it is built
  • Preliminaries = Fixed + Months × Monthly cost
Usual mistake
You priced 78 weeks at the monthly rate. The rate is per month: turn days into months.
At work
The estimator reads the period from the programme and prices the site per month, plus what is paid once.

Task 4

Provisional sums go in as stated

Theory (6 min)
Rule
A provisional sum is the client's figure. Enter it as stated; the Engineer decides how it is spent.
How it is built
  • Net cost = Direct Cost
Usual mistake
PS.01 carries the MEP offer. A provisional sum is entered as stated; the offer is not instructed work.
At work
The estimator copies each provisional sum from the tender documents and files any offer for after award.

Task 5

Mark-ups added once: the tender sum

Theory (8 min)
Rule
Mark-ups go on once, at the end. Each on the running total, over the whole net cost.
How it is built
  • Tender sum = Grand Total
Usual mistake
The mark-ups sit on Sum of positions. Set each base to Running total incl. rows above.
At work
The estimating manager sets the mark-ups at the tender review, on the net cost the estimator presents.