Въведение в курса · 3 мин
Ремонт на къща: калкулация, оферта и промени (Австралия)
Coolibah Crescent renovation · Single-storey brick house · Измислен проект
You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.
- Work
- New bathroom, kitchen and rear room
- Contract
- Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
- Story
- November 2026 to February 2027
- Работа в ERP
- Задачи: 5, около 3 ч 5 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- The ownersYour clients
- Their plan and wish listЗадача 1
- Dearer tiles and a nicheЗадача 5
- Your subcontractorsPlumber, electrician, tiler and others
- Quotes, some with GSTЗадача 2
Тръгва от вас
- QuoteЗадача 3
- Payment schedule and deposit claimЗадача 4
- Variation to signЗадача 5
Вашият път през проекта
Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.
Measure and cost
Задача 1 · 35 мин
Измерване по плана: плочки, плочи, перваз, корниз
- Вашият резултат
- Tiles, board, skirting and cornice to order
- Документ
- The owners' plan
- В ERP
- Bill of Quantities
Measure and cost
Задача 2 · 40 мин
Изграждане на разходите по дейности
- Вашият резултат
- Direct cost (what the job costs you), without GST, the 10 % goods and services tax
- Документ
- Your hours, subcontract quotes, supplier prices
- В ERP
- Bill of Quantities
The quote
Задача 3 · 40 мин
Офертата: марж, позиции PC, условни суми и GST
- Вашият резултат
- The quote price, GST included
- Документ
- Allowances (sums for items not yet chosen) and your margin target
- В ERP
- Bill of Quantities, Markups
Under contract
Задача 4 · 35 мин
Плащателният график: лимит на аванса и етапни плащания
- Вашият резултат
- The payment schedule and the deposit claim
- Документ
- Contract template, NSW deposit rule
- В ERP
- Contracts, Progress Claims
Under contract
Задача 5 · 35 мин
Остойностяване на промяна: корекция на PC и ниша
- Вашият резултат
- The variation, signed off
- Документ
- The owners' tile choice and the niche
- В ERP
- Variations
How a measured room becomes a contract price
Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.