Въведение в курса · 3 мин

Ремонт на къща: калкулация, оферта и промени (Австралия)

Coolibah Crescent renovation · Single-storey brick house · Измислен проект

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Започнете задача 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Работа в ERP
Задачи: 5, около 3 ч 5 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • The ownersYour clients
    • Their plan and wish listЗадача 1
    • Dearer tiles and a nicheЗадача 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTЗадача 2
ВиеBuilder, estimating your own jobs

Тръгва от вас

    • QuoteЗадача 3
    • Payment schedule and deposit claimЗадача 4
    • Variation to signЗадача 5
    The ownersSign and pay

Вашият път през проекта

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Задача 1 · 35 мин

    Измерване по плана: плочки, плочи, перваз, корниз

    Вашият резултат
    Tiles, board, skirting and cornice to order
    Документ
    The owners' plan
    В ERP
    Bill of Quantities
  2. Measure and cost

    Задача 2 · 40 мин

    Изграждане на разходите по дейности

    Вашият резултат
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Документ
    Your hours, subcontract quotes, supplier prices
    В ERP
    Bill of Quantities
  3. The quote

    Задача 3 · 40 мин

    Офертата: марж, позиции PC, условни суми и GST

    Вашият резултат
    The quote price, GST included
    Документ
    Allowances (sums for items not yet chosen) and your margin target
    В ERP
    Bill of Quantities, Markups
  4. Under contract

    Задача 4 · 35 мин

    Плащателният график: лимит на аванса и етапни плащания

    Вашият резултат
    The payment schedule and the deposit claim
    Документ
    Contract template, NSW deposit rule
    В ERP
    Contracts, Progress Claims
  5. Under contract

    Задача 5 · 35 мин

    Остойностяване на промяна: корекция на PC и ниша

    Вашият резултат
    The variation, signed off
    Документ
    The owners' tile choice and the niche
    В ERP
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Задача 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Задача 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Задача 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Задача 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.