Renovarea unei case: deviz, ofertă și variații (Australia)
Coolibah Crescent renovation · Single-storey brick house · Proiect fictiv
You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.
- Work
- New bathroom, kitchen and rear room
- Contract
- Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
- Story
- November 2026 to February 2027
- Lucru în ERP
- 5 sarcini, circa 3 h 5 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- The ownersYour clients
- Their plan and wish listSarcina 1
- Dearer tiles and a nicheSarcina 5
- Your subcontractorsPlumber, electrician, tiler and others
- Quotes, some with GSTSarcina 2
Pleacă de la tine
- QuoteSarcina 3
- Payment schedule and deposit claimSarcina 4
- Variation to signSarcina 5
Traseul tău prin proiect
Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.
Measure and cost
Sarcina 1 · 35 min
Măsurare de pe plan: faianță, plăci, plintă, cornișă
- Produci
- Tiles, board, skirting and cornice to order
- Document
- The owners' plan
- În ERP
- Bill of Quantities
Measure and cost
Sarcina 2 · 40 min
Construiește costurile pe meserii
- Produci
- Direct cost (what the job costs you), without GST, the 10 % goods and services tax
- Document
- Your hours, subcontract quotes, supplier prices
- În ERP
- Bill of Quantities
The quote
Sarcina 3 · 40 min
Oferta: adaos, poziții PC, sume provizorii și GST
- Produci
- The quote price, GST included
- Document
- Allowances (sums for items not yet chosen) and your margin target
- În ERP
- Bill of Quantities, Markups
Under contract
Sarcina 4 · 35 min
Eșalonarea plăților: limita avansului și plățile pe etape
- Produci
- The payment schedule and the deposit claim
- Document
- Contract template, NSW deposit rule
- În ERP
- Contracts, Progress Claims
Under contract
Sarcina 5 · 35 min
Evaluarea unei variații: ajustarea PC și o nișă
- Produci
- The variation, signed off
- Document
- The owners' tile choice and the niche
- În ERP
- Variations
How a measured room becomes a contract price
Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.