Renovarea unei case: deviz, ofertă și variații (Australia)

Coolibah Crescent renovation · Single-storey brick house · Proiect fictiv

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Începe sarcina 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Lucru în ERP
5 sarcini, circa 3 h 5 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • The ownersYour clients
    • Their plan and wish listSarcina 1
    • Dearer tiles and a nicheSarcina 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTSarcina 2
TuBuilder, estimating your own jobs

Pleacă de la tine

    • QuoteSarcina 3
    • Payment schedule and deposit claimSarcina 4
    • Variation to signSarcina 5
    The ownersSign and pay

Traseul tău prin proiect

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Sarcina 1 · 35 min

    Măsurare de pe plan: faianță, plăci, plintă, cornișă

    Produci
    Tiles, board, skirting and cornice to order
    Document
    The owners' plan
    În ERP
    Bill of Quantities
  2. Measure and cost

    Sarcina 2 · 40 min

    Construiește costurile pe meserii

    Produci
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Document
    Your hours, subcontract quotes, supplier prices
    În ERP
    Bill of Quantities
  3. The quote

    Sarcina 3 · 40 min

    Oferta: adaos, poziții PC, sume provizorii și GST

    Produci
    The quote price, GST included
    Document
    Allowances (sums for items not yet chosen) and your margin target
    În ERP
    Bill of Quantities, Markups
  4. Under contract

    Sarcina 4 · 35 min

    Eșalonarea plăților: limita avansului și plățile pe etape

    Produci
    The payment schedule and the deposit claim
    Document
    Contract template, NSW deposit rule
    În ERP
    Contracts, Progress Claims
  5. Under contract

    Sarcina 5 · 35 min

    Evaluarea unei variații: ajustarea PC și o nișă

    Produci
    The variation, signed off
    Document
    The owners' tile choice and the niche
    În ERP
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Sarcina 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Sarcina 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Sarcina 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Sarcina 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.