Pagpapaayos ng bahay: estimate, quote at mga variation (Australia)

Coolibah Crescent renovation · Single-storey brick house · Kathang-isip na proyekto

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Simulan ang gawain 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Trabaho sa ERP
5 gawain, mga 3 oras 5 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • The ownersYour clients
    • Their plan and wish listGawain 1
    • Dearer tiles and a nicheGawain 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTGawain 2
IkawBuilder, estimating your own jobs

Lumalabas sa iyo

    • QuoteGawain 3
    • Payment schedule and deposit claimGawain 4
    • Variation to signGawain 5
    The ownersSign and pay

Ang ruta mo sa proyekto

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Gawain 1 · 35 min

    Sukatin mula sa plano: tiles, board, skirting, cornice

    Ang gagawin mo
    Tiles, board, skirting and cornice to order
    Dokumento
    The owners' plan
    Sa ERP
    Bill of Quantities
  2. Measure and cost

    Gawain 2 · 40 min

    Buuin ang gastos ng bawat trade

    Ang gagawin mo
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Dokumento
    Your hours, subcontract quotes, supplier prices
    Sa ERP
    Bill of Quantities
  3. The quote

    Gawain 3 · 40 min

    Ang quote: margin, mga PC item, provisional sum at GST

    Ang gagawin mo
    The quote price, GST included
    Dokumento
    Allowances (sums for items not yet chosen) and your margin target
    Sa ERP
    Bill of Quantities, Markups
  4. Under contract

    Gawain 4 · 35 min

    Ang iskedyul ng bayad: limitasyon sa deposito at mga bayad kada yugto

    Ang gagawin mo
    The payment schedule and the deposit claim
    Dokumento
    Contract template, NSW deposit rule
    Sa ERP
    Contracts, Progress Claims
  5. Under contract

    Gawain 5 · 35 min

    Presyuhan ang isang variation: ang pag-aayos ng PC at isang niche

    Ang gagawin mo
    The variation, signed off
    Dokumento
    The owners' tile choice and the niche
    Sa ERP
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Gawain 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Gawain 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Gawain 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Gawain 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.