Kodu renoveerimine: hinnastamine, pakkumine ja muudatused (Austraalia)

Coolibah Crescent renovation · Single-storey brick house · Väljamõeldud projekt

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Alusta ülesannet 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Töö ERP-s
Ülesandeid 5, umbes 3 h 5 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • The ownersYour clients
    • Their plan and wish listÜlesanne 1
    • Dearer tiles and a nicheÜlesanne 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTÜlesanne 2
SinaBuilder, estimating your own jobs

Läheb sinult

    • QuoteÜlesanne 3
    • Payment schedule and deposit claimÜlesanne 4
    • Variation to signÜlesanne 5
    The ownersSign and pay

Sinu tee läbi projekti

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Ülesanne 1 · 35 min

    Mõõda plaanilt: plaadid, kipsplaat, põrandaliistud, laeliistud

    Sinu tulemus
    Tiles, board, skirting and cornice to order
    Dokument
    The owners' plan
    ERP-s
    Bill of Quantities
  2. Measure and cost

    Ülesanne 2 · 40 min

    Koosta tööliikide kulu

    Sinu tulemus
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Dokument
    Your hours, subcontract quotes, supplier prices
    ERP-s
    Bill of Quantities
  3. The quote

    Ülesanne 3 · 40 min

    Pakkumine: marginaal, PC-kirjed, tingimuslikud summad ja GST

    Sinu tulemus
    The quote price, GST included
    Dokument
    Allowances (sums for items not yet chosen) and your margin target
    ERP-s
    Bill of Quantities, Markups
  4. Under contract

    Ülesanne 4 · 35 min

    Maksegraafik: ettemaksu piirang ja etapimaksed

    Sinu tulemus
    The payment schedule and the deposit claim
    Dokument
    Contract template, NSW deposit rule
    ERP-s
    Contracts, Progress Claims
  5. Under contract

    Ülesanne 5 · 35 min

    Hinnasta muudatus: PC korrigeerimine ja nišš

    Sinu tulemus
    The variation, signed off
    Dokument
    The owners' tile choice and the niche
    ERP-s
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Ülesanne 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Ülesanne 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Ülesanne 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Ülesanne 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.