Úvod do kurzu · 3 min
Rekonstrukce domu: rozpočet, nabídka a vícepráce (Austrálie)
Coolibah Crescent renovation · Single-storey brick house · Smyšlený projekt
You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.
- Work
- New bathroom, kitchen and rear room
- Contract
- Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
- Story
- November 2026 to February 2027
- Práce v ERP
- Úlohy: 5, asi 3 h 5 min
Kdo komu co předává
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Přichází k vám
- The ownersYour clients
- Their plan and wish listÚloha 1
- Dearer tiles and a nicheÚloha 5
- Your subcontractorsPlumber, electrician, tiler and others
- Quotes, some with GSTÚloha 2
Odchází od vás
- QuoteÚloha 3
- Payment schedule and deposit claimÚloha 4
- Variation to signÚloha 5
Vaše cesta zakázkou
Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.
Measure and cost
Úloha 1 · 35 min
Výměra z plánu: dlaždice, desky, sokl, římsa
- Výstup
- Tiles, board, skirting and cornice to order
- Dokument
- The owners' plan
- V ERP
- Bill of Quantities
Measure and cost
Úloha 2 · 40 min
Sestavení nákladů řemesel
- Výstup
- Direct cost (what the job costs you), without GST, the 10 % goods and services tax
- Dokument
- Your hours, subcontract quotes, supplier prices
- V ERP
- Bill of Quantities
The quote
Úloha 3 · 40 min
Nabídka: marže, položky PC, prozatímní částky a GST
- Výstup
- The quote price, GST included
- Dokument
- Allowances (sums for items not yet chosen) and your margin target
- V ERP
- Bill of Quantities, Markups
Under contract
Úloha 4 · 35 min
Platební kalendář: limit zálohy a etapové platby
- Výstup
- The payment schedule and the deposit claim
- Dokument
- Contract template, NSW deposit rule
- V ERP
- Contracts, Progress Claims
Under contract
Úloha 5 · 35 min
Ocenění změny: úprava PC a výklenek
- Výstup
- The variation, signed off
- Dokument
- The owners' tile choice and the niche
- V ERP
- Variations
How a measured room becomes a contract price
Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.
Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.
Stručně. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.