Rekonstrukce domu: rozpočet, nabídka a vícepráce (Austrálie)

Coolibah Crescent renovation · Single-storey brick house · Smyšlený projekt

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Začít úlohu 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Práce v ERP
Úlohy: 5, asi 3 h 5 min

Kdo komu co předává

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Přichází k vám

  • The ownersYour clients
    • Their plan and wish listÚloha 1
    • Dearer tiles and a nicheÚloha 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTÚloha 2
VyBuilder, estimating your own jobs

Odchází od vás

    • QuoteÚloha 3
    • Payment schedule and deposit claimÚloha 4
    • Variation to signÚloha 5
    The ownersSign and pay

Vaše cesta zakázkou

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Úloha 1 · 35 min

    Výměra z plánu: dlaždice, desky, sokl, římsa

    Výstup
    Tiles, board, skirting and cornice to order
    Dokument
    The owners' plan
    V ERP
    Bill of Quantities
  2. Measure and cost

    Úloha 2 · 40 min

    Sestavení nákladů řemesel

    Výstup
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Dokument
    Your hours, subcontract quotes, supplier prices
    V ERP
    Bill of Quantities
  3. The quote

    Úloha 3 · 40 min

    Nabídka: marže, položky PC, prozatímní částky a GST

    Výstup
    The quote price, GST included
    Dokument
    Allowances (sums for items not yet chosen) and your margin target
    V ERP
    Bill of Quantities, Markups
  4. Under contract

    Úloha 4 · 35 min

    Platební kalendář: limit zálohy a etapové platby

    Výstup
    The payment schedule and the deposit claim
    Dokument
    Contract template, NSW deposit rule
    V ERP
    Contracts, Progress Claims
  5. Under contract

    Úloha 5 · 35 min

    Ocenění změny: úprava PC a výklenek

    Výstup
    The variation, signed off
    Dokument
    The owners' tile choice and the niche
    V ERP
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Úloha 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Úloha 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Úloha 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Úloha 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.