Kurssin johdanto · 3 min

Kotiremontti: kustannuslaskelma, tarjous ja muutostyöt (Australia)

Coolibah Crescent renovation · Single-storey brick house · Kuvitteellinen hanke

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Aloita tehtävä 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Työ ERP:ssä
Tehtäviä 5, noin 3 t 5 min

Kuka antaa mitä kenelle

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tulee sinulle

  • The ownersYour clients
    • Their plan and wish listTehtävä 1
    • Dearer tiles and a nicheTehtävä 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTTehtävä 2
SinäBuilder, estimating your own jobs

Lähtee sinulta

    • QuoteTehtävä 3
    • Payment schedule and deposit claimTehtävä 4
    • Variation to signTehtävä 5
    The ownersSign and pay

Reittisi hankkeen läpi

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Tehtävä 1 · 35 min

    Mittaa piirustuksesta: laatat, levyt, jalkalistat, kattolistat

    Tuotat
    Tiles, board, skirting and cornice to order
    Asiakirja
    The owners' plan
    ERP:ssä
    Bill of Quantities
  2. Measure and cost

    Tehtävä 2 · 40 min

    Kokoa ammattialojen kustannukset

    Tuotat
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Asiakirja
    Your hours, subcontract quotes, supplier prices
    ERP:ssä
    Bill of Quantities
  3. The quote

    Tehtävä 3 · 40 min

    Tarjous: kate, PC-erät, arvioerät ja GST

    Tuotat
    The quote price, GST included
    Asiakirja
    Allowances (sums for items not yet chosen) and your margin target
    ERP:ssä
    Bill of Quantities, Markups
  4. Under contract

    Tehtävä 4 · 35 min

    Maksuerätaulukko: ennakkomaksun katto ja vaihemaksut

    Tuotat
    The payment schedule and the deposit claim
    Asiakirja
    Contract template, NSW deposit rule
    ERP:ssä
    Contracts, Progress Claims
  5. Under contract

    Tehtävä 5 · 35 min

    Hinnoittele muutostyö: PC-oikaisu ja syvennys

    Tuotat
    The variation, signed off
    Asiakirja
    The owners' tile choice and the niche
    ERP:ssä
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Tehtävä 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Tehtävä 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Tehtävä 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Tehtävä 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.

Lyhyesti. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.