Uvod u tečaj · 3 min
Obnova kuće: procjena, ponuda i izmjene (Australija)
Coolibah Crescent renovation · Single-storey brick house · Izmišljeni projekt
You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.
- Work
- New bathroom, kitchen and rear room
- Contract
- Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
- Story
- November 2026 to February 2027
- Rad u ERP-u
- Zadataka: 5, oko 3 h 5 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- The ownersYour clients
- Their plan and wish listZadatak 1
- Dearer tiles and a nicheZadatak 5
- Your subcontractorsPlumber, electrician, tiler and others
- Quotes, some with GSTZadatak 2
Odlazi od vas
- QuoteZadatak 3
- Payment schedule and deposit claimZadatak 4
- Variation to signZadatak 5
Vaš put kroz projekt
Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.
Measure and cost
Zadatak 1 · 35 min
Mjerenje s nacrta: pločice, ploče, letvice, vijenac
- Vaš rezultat
- Tiles, board, skirting and cornice to order
- Dokument
- The owners' plan
- U ERP-u
- Bill of Quantities
Measure and cost
Zadatak 2 · 40 min
Izradi troškove po radovima
- Vaš rezultat
- Direct cost (what the job costs you), without GST, the 10 % goods and services tax
- Dokument
- Your hours, subcontract quotes, supplier prices
- U ERP-u
- Bill of Quantities
The quote
Zadatak 3 · 40 min
Ponuda: marža, stavke PC, privremeni iznosi i GST
- Vaš rezultat
- The quote price, GST included
- Dokument
- Allowances (sums for items not yet chosen) and your margin target
- U ERP-u
- Bill of Quantities, Markups
Under contract
Zadatak 4 · 35 min
Raspored plaćanja: ograničenje pologa i plaćanja po fazama
- Vaš rezultat
- The payment schedule and the deposit claim
- Dokument
- Contract template, NSW deposit rule
- U ERP-u
- Contracts, Progress Claims
Under contract
Zadatak 5 · 35 min
Vrednovanje izmjene: usklađenje PC-a i niša
- Vaš rezultat
- The variation, signed off
- Dokument
- The owners' tile choice and the niche
- U ERP-u
- Variations
How a measured room becomes a contract price
Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.