Course introduction · 3 min

Home renovation: estimate, quote and variations (Australia)

Coolibah Crescent renovation · Single-storey brick house · Fictional project

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Start task 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Work in the ERP
5 tasks, about 3 h 5 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • The ownersYour clients
    • Their plan and wish listTask 1
    • Dearer tiles and a nicheTask 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTTask 2
YouBuilder, estimating your own jobs

Goes from you

    • QuoteTask 3
    • Payment schedule and deposit claimTask 4
    • Variation to signTask 5
    The ownersSign and pay

Your route through the job

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Task 1 · 35 min

    Measure from the plan: tiles, board, skirting, cornice

    You produce
    Tiles, board, skirting and cornice to order
    Document
    The owners' plan
    In the ERP
    Bill of Quantities
  2. Measure and cost

    Task 2 · 40 min

    Build up the trade costs

    You produce
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Document
    Your hours, subcontract quotes, supplier prices
    In the ERP
    Bill of Quantities
  3. The quote

    Task 3 · 40 min

    The quote: margin, PC items, provisional sums and GST

    You produce
    The quote price, GST included
    Document
    Allowances (sums for items not yet chosen) and your margin target
    In the ERP
    Bill of Quantities, Markups
  4. Under contract

    Task 4 · 35 min

    The payment schedule: deposit cap and stage payments

    You produce
    The payment schedule and the deposit claim
    Document
    Contract template, NSW deposit rule
    In the ERP
    Contracts, Progress Claims
  5. Under contract

    Task 5 · 35 min

    Price a variation: the PC adjustment and a niche

    You produce
    The variation, signed off
    Document
    The owners' tile choice and the niche
    In the ERP
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Task 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Task 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Task 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Task 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Blue is what the task adds; grey is carried over from before.

In short. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.