Course introduction · 3 min
Home renovation: estimate, quote and variations (Australia)
Coolibah Crescent renovation · Single-storey brick house · Fictional project
You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.
- Work
- New bathroom, kitchen and rear room
- Contract
- Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
- Story
- November 2026 to February 2027
- Work in the ERP
- 5 tasks, about 3 h 5 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- The ownersYour clients
- Their plan and wish listTask 1
- Dearer tiles and a nicheTask 5
- Your subcontractorsPlumber, electrician, tiler and others
- Quotes, some with GSTTask 2
Goes from you
- QuoteTask 3
- Payment schedule and deposit claimTask 4
- Variation to signTask 5
Your route through the job
Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.
Measure and cost
Task 1 · 35 min
Measure from the plan: tiles, board, skirting, cornice
- You produce
- Tiles, board, skirting and cornice to order
- Document
- The owners' plan
- In the ERP
- Bill of Quantities
Measure and cost
Task 2 · 40 min
Build up the trade costs
- You produce
- Direct cost (what the job costs you), without GST, the 10 % goods and services tax
- Document
- Your hours, subcontract quotes, supplier prices
- In the ERP
- Bill of Quantities
The quote
Task 3 · 40 min
The quote: margin, PC items, provisional sums and GST
- You produce
- The quote price, GST included
- Document
- Allowances (sums for items not yet chosen) and your margin target
- In the ERP
- Bill of Quantities, Markups
Under contract
Task 4 · 35 min
The payment schedule: deposit cap and stage payments
- You produce
- The payment schedule and the deposit claim
- Document
- Contract template, NSW deposit rule
- In the ERP
- Contracts, Progress Claims
Under contract
Task 5 · 35 min
Price a variation: the PC adjustment and a niche
- You produce
- The variation, signed off
- Document
- The owners' tile choice and the niche
- In the ERP
- Variations
How a measured room becomes a contract price
Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.
Blue is what the task adds; grey is carried over from before.
In short. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.