Гэрийн засвар: тооцоо, үнийн санал ба өөрчлөлт (Австрали)

Coolibah Crescent renovation · Single-storey brick house · Зохиомол төсөл

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

1-р даалгаврыг эхлэх

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 3 цаг 5 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • The ownersYour clients
    • Their plan and wish listДаалгавар 1
    • Dearer tiles and a nicheДаалгавар 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTДаалгавар 2
ТаBuilder, estimating your own jobs

Танаас гардаг

    • QuoteДаалгавар 3
    • Payment schedule and deposit claimДаалгавар 4
    • Variation to signДаалгавар 5
    The ownersSign and pay

Төслөөр явах таны зам

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Даалгавар 1 · 35 мин

    Төлөвлөгөөнөөс хэмжих: плитка, хавтан, плинтус, карниз

    Үр дүн
    Tiles, board, skirting and cornice to order
    Баримт бичиг
    The owners' plan
    ERP дээр
    Bill of Quantities
  2. Measure and cost

    Даалгавар 2 · 40 мин

    Мэргэжлийн ажлын өртгийг гаргах

    Үр дүн
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Баримт бичиг
    Your hours, subcontract quotes, supplier prices
    ERP дээр
    Bill of Quantities
  3. The quote

    Даалгавар 3 · 40 мин

    Үнийн санал: ашиг, PC зүйл, түр дүн ба GST

    Үр дүн
    The quote price, GST included
    Баримт бичиг
    Allowances (sums for items not yet chosen) and your margin target
    ERP дээр
    Bill of Quantities, Markups
  4. Under contract

    Даалгавар 4 · 35 мин

    Төлбөрийн хуваарь: урьдчилгааны дээд хязгаар ба үе шатны төлбөр

    Үр дүн
    The payment schedule and the deposit claim
    Баримт бичиг
    Contract template, NSW deposit rule
    ERP дээр
    Contracts, Progress Claims
  5. Under contract

    Даалгавар 5 · 35 мин

    Өөрчлөлтийг үнэлэх: PC-ийн засвар ба хонхор

    Үр дүн
    The variation, signed off
    Баримт бичиг
    The owners' tile choice and the niche
    ERP дээр
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Даалгавар 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Даалгавар 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Даалгавар 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Даалгавар 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.