Inleiding tot de cursus · 3 min
Woningrenovatie: raming, offerte en meerwerk (Australië)
Coolibah Crescent renovation · Single-storey brick house · Fictief project
You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.
- Work
- New bathroom, kitchen and rear room
- Contract
- Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
- Story
- November 2026 to February 2027
- Werk in de ERP
- 5 opdrachten, ongeveer 3 u 5 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- The ownersYour clients
- Their plan and wish listOpdracht 1
- Dearer tiles and a nicheOpdracht 5
- Your subcontractorsPlumber, electrician, tiler and others
- Quotes, some with GSTOpdracht 2
Gaat van u uit
- QuoteOpdracht 3
- Payment schedule and deposit claimOpdracht 4
- Variation to signOpdracht 5
Uw route door het project
Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.
Measure and cost
Opdracht 1 · 35 min
Meten uit de plattegrond: tegels, plaat, plinten, kroonlijst
- U levert
- Tiles, board, skirting and cornice to order
- Document
- The owners' plan
- In de ERP
- Bill of Quantities
Measure and cost
Opdracht 2 · 40 min
De kosten per vak opbouwen
- U levert
- Direct cost (what the job costs you), without GST, the 10 % goods and services tax
- Document
- Your hours, subcontract quotes, supplier prices
- In de ERP
- Bill of Quantities
The quote
Opdracht 3 · 40 min
De offerte: marge, PC-posten, stelposten en GST
- U levert
- The quote price, GST included
- Document
- Allowances (sums for items not yet chosen) and your margin target
- In de ERP
- Bill of Quantities, Markups
Under contract
Opdracht 4 · 35 min
Het betalingsschema: limiet voor de aanbetaling en termijnbetalingen
- U levert
- The payment schedule and the deposit claim
- Document
- Contract template, NSW deposit rule
- In de ERP
- Contracts, Progress Claims
Under contract
Opdracht 5 · 35 min
Meerwerk prijzen: de PC-aanpassing en een nis
- U levert
- The variation, signed off
- Document
- The owners' tile choice and the niche
- In de ERP
- Variations
How a measured room becomes a contract price
Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.