Inleiding tot de cursus · 3 min

Woningrenovatie: raming, offerte en meerwerk (Australië)

Coolibah Crescent renovation · Single-storey brick house · Fictief project

You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.

Start opdracht 1

Work
New bathroom, kitchen and rear room
Contract
Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
Story
November 2026 to February 2027
Werk in de ERP
5 opdrachten, ongeveer 3 u 5 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • The ownersYour clients
    • Their plan and wish listOpdracht 1
    • Dearer tiles and a nicheOpdracht 5
  • Your subcontractorsPlumber, electrician, tiler and others
    • Quotes, some with GSTOpdracht 2
UBuilder, estimating your own jobs

Gaat van u uit

    • QuoteOpdracht 3
    • Payment schedule and deposit claimOpdracht 4
    • Variation to signOpdracht 5
    The ownersSign and pay

Uw route door het project

Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.

  1. Measure and cost

    Opdracht 1 · 35 min

    Meten uit de plattegrond: tegels, plaat, plinten, kroonlijst

    U levert
    Tiles, board, skirting and cornice to order
    Document
    The owners' plan
    In de ERP
    Bill of Quantities
  2. Measure and cost

    Opdracht 2 · 40 min

    De kosten per vak opbouwen

    U levert
    Direct cost (what the job costs you), without GST, the 10 % goods and services tax
    Document
    Your hours, subcontract quotes, supplier prices
    In de ERP
    Bill of Quantities
  3. The quote

    Opdracht 3 · 40 min

    De offerte: marge, PC-posten, stelposten en GST

    U levert
    The quote price, GST included
    Document
    Allowances (sums for items not yet chosen) and your margin target
    In de ERP
    Bill of Quantities, Markups
  4. Under contract

    Opdracht 4 · 35 min

    Het betalingsschema: limiet voor de aanbetaling en termijnbetalingen

    U levert
    The payment schedule and the deposit claim
    Document
    Contract template, NSW deposit rule
    In de ERP
    Contracts, Progress Claims
  5. Under contract

    Opdracht 5 · 35 min

    Meerwerk prijzen: de PC-aanpassing en een nis

    U levert
    The variation, signed off
    Document
    The owners' tile choice and the niche
    In de ERP
    Variations

How a measured room becomes a contract price

Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.

MaterialsSubcontractorsYour labour
Opdracht 2CostYour hours, the quotes and the materials, all without GST.
GSTMarginPC items and provisional sumsCost
Opdracht 3QuoteAllowances in, margin as a markup on cost, GST last.
Final paymentStage paymentsDeposit
Opdracht 4PaymentsDeposit within the legal cap, stages, then the balance.
VariationContract price
Opdracht 5VariationThe PC difference (prime cost: the gap between the allowance and what the owners chose) plus new work, with margin and GST.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.