Introduktion till kursen · 3 min
Husrenovering: kalkyl, offert och ändringar (Australien)
Coolibah Crescent renovation · Single-storey brick house · Fiktivt projekt
You are the builder: a small firm of you and one labourer, and you do your own estimating. In five tasks you take a kitchen, bathroom and rear room renovation from the owners' plan to a signed quote, then a payment schedule (when the owners pay each part) that the law of New South Wales allows, and the first variation, a change the owners ask for after signing.
- Work
- New bathroom, kitchen and rear room
- Contract
- Fixed-price home building contract on an HIA template (the Housing Industry Association's standard form), NSW
- Story
- November 2026 to February 2027
- Arbete i ERP
- 5 uppgifter, cirka 3 h 5 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- The ownersYour clients
- Their plan and wish listUppgift 1
- Dearer tiles and a nicheUppgift 5
- Your subcontractorsPlumber, electrician, tiler and others
- Quotes, some with GSTUppgift 2
Går från dig
- QuoteUppgift 3
- Payment schedule and deposit claimUppgift 4
- Variation to signUppgift 5
Din väg genom projektet
Two tasks to measure and cost the job, one to turn cost into a price, two once the contract is signed. Start with task 1: in the Bill of Quantities you measure the tiles, board, skirting and cornice to order from the owners' plan.
Measure and cost
Uppgift 1 · 35 min
Mäta från ritningen: kakel, skiva, golvlist, taklist
- Du tar fram
- Tiles, board, skirting and cornice to order
- Dokument
- The owners' plan
- I ERP
- Bill of Quantities
Measure and cost
Uppgift 2 · 40 min
Bygg upp yrkeskostnaderna
- Du tar fram
- Direct cost (what the job costs you), without GST, the 10 % goods and services tax
- Dokument
- Your hours, subcontract quotes, supplier prices
- I ERP
- Bill of Quantities
The quote
Uppgift 3 · 40 min
Offerten: marginal, PC-poster, provisoriska summor och GST
- Du tar fram
- The quote price, GST included
- Dokument
- Allowances (sums for items not yet chosen) and your margin target
- I ERP
- Bill of Quantities, Markups
Under contract
Uppgift 4 · 35 min
Betalningsplanen: handpenningstak och etappbetalningar
- Du tar fram
- The payment schedule and the deposit claim
- Dokument
- Contract template, NSW deposit rule
- I ERP
- Contracts, Progress Claims
Under contract
Uppgift 5 · 35 min
Prissätt en ändring: PC-justeringen och en nisch
- Du tar fram
- The variation, signed off
- Dokument
- The owners' tile choice and the niche
- I ERP
- Variations
How a measured room becomes a contract price
Each step below is one task, in the order the money is built. The quote fixes the price; the schedule splits it; a variation moves it.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Net first, waste once. Cost without GST. Margin is not markup. GST last, once.