OpenConstruction Academy
Вход / Регистрация
BG

Въведение в курса · 3 мин

Преизмерване, претенция и получаване на плащане (Австралия, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Започнете задача 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Измислен проект
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Работа в ERP
Задачи: 6, около 2 ч 40 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • Site managerYour firm, on site
    • Draft claim 7Задача 2
  • SuperintendentAssesses the claim
    • Site instruction 14Задача 3
    • Payment scheduleЗадача 6
  • Commercial managerYour firm
    • Annexure termsЗадача 5
ВиеQuantity surveyor, head contractor

Тръгва от вас

    • Payment claim 7Задача 4
    • Amount payableЗадача 5
    PrincipalPays the claim
    • Last day to applyЗадача 6
    AdjudicatorUnder the NSW Act

Проектът и хората са измислени. Портретите са генерирани.

Вашият път през проекта

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Задача 1 · 30 мин

    Преизмерете плочата на Level 1 за претенцията

    Вашият резултат
    Net quantities for the Level 1 slab
    Документ
    Bill lines 3.1 to 3.4
    В ERP
    Bill of Quantities
  2. Measure and value

    Задача 2 · 25 мин

    Оценете сметката и определете стойността на търговската позиция към момента

    Вашият резултат
    The concrete structure trade to date
    Документ
    Priced bill against the draft claim
    В ERP
    Bill of Quantities
  3. The change

    Задача 3 · 25 мин

    Оценете удебеляването на плочата като промяна

    Вашият резултат
    Variation 14 (the priced change)
    Документ
    Site instruction 14
    В ERP
    Variations
  4. The claim

    Задача 4 · 30 мин

    Претенция за плащане 7 за посочения месец

    Вашият резултат
    Payment claim 7 with GST
    Документ
    Schedule of values, claims 1 to 6
    В ERP
    Contracts, Progress Claims
  5. The claim

    Задача 5 · 25 мин

    Задържане, гаранция и действително подлежащата на плащане сума

    Вашият резултат
    Retention and the amount payable
    Документ
    Annexure Part A
    В ERP
    Contracts, Progress Claims
  6. The clock

    Задача 6 · 25 мин

    Платежният график и законовото отброяване на времето

    Вашият резултат
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Документ
    The payment schedule
    В ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Задача 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Задача 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Задача 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Задача 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.