Кайра өлчөө, доомат жана төлөмдү алуу (Австралия, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

1-тапшырманы баштоо

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Ойдон чыгарылган долбоор
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
ERPдеги иш
Тапшырмалар: 6, болжол менен 2 саат 40 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Site managerYour firm, on site
    • Draft claim 72-тапшырма
  • SuperintendentAssesses the claim
    • Site instruction 143-тапшырма
    • Payment schedule6-тапшырма
  • Commercial managerYour firm
    • Annexure terms5-тапшырма
СизQuantity surveyor, head contractor

Сизден кетет

    • Payment claim 74-тапшырма
    • Amount payable5-тапшырма
    PrincipalPays the claim
    • Last day to apply6-тапшырма
    AdjudicatorUnder the NSW Act

Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.

Долбоор боюнча жолуңуз

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    1-тапшырма · 30 мүн

    Доомат үчүн 1-деңгээлдин плитасын кайра өлчөө

    Натыйжа
    Net quantities for the Level 1 slab
    Документ
    Bill lines 3.1 to 3.4
    ERPде
    Bill of Quantities
  2. Measure and value

    2-тапшырма · 25 мүн

    Сметаны баалоо жана иш түрүн ушул күнгө чейин баалоо

    Натыйжа
    The concrete structure trade to date
    Документ
    Priced bill against the draft claim
    ERPде
    Bill of Quantities
  3. The change

    3-тапшырма · 25 мүн

    Плитанын калыңдатылышын өзгөртүү катары баалоо

    Натыйжа
    Variation 14 (the priced change)
    Документ
    Site instruction 14
    ERPде
    Variations
  4. The claim

    4-тапшырма · 30 мүн

    Аталган ай үчүн 7-төлөм доомат

    Натыйжа
    Payment claim 7 with GST
    Документ
    Schedule of values, claims 1 to 6
    ERPде
    Contracts, Progress Claims
  5. The claim

    5-тапшырма · 25 мүн

    Кармоо, күрөө жана чындыгында төлөнүүчү сумма

    Натыйжа
    Retention and the amount payable
    Документ
    Annexure Part A
    ERPде
    Contracts, Progress Claims
  6. The clock

    6-тапшырма · 25 мүн

    Төлөм графиги жана мыйзамдык саат

    Натыйжа
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Документ
    The payment schedule
    ERPде
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
1-тапшырмаNet quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
2-тапшырмаTrade valueEvery section at bill rates, to date.
GSTVariation 14This claim
4-тапшырмаClaim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
5-тапшырмаPayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.