Panimula ng kurso · 3 min
I-remeasure, mag-claim, at mabayaran (Australia, AS 4000)
You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.
Kathang-isip na proyekto- Building
- Two-storey outpatient clinic, Class 9a, concrete frame
- Contract
- AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
- Story
- November 2026 to January 2027
- Trabaho sa ERP
- 6 gawain, mga 2 oras 40 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Site managerYour firm, on site
- Draft claim 7Gawain 2
- SuperintendentAssesses the claim
- Site instruction 14Gawain 3
- Payment scheduleGawain 6
Commercial managerYour firm- Annexure termsGawain 5
IkawQuantity surveyor, head contractorLumalabas sa iyo
- Payment claim 7Gawain 4
- Amount payableGawain 5
- Last day to applyGawain 6
Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.
Ang ruta mo sa proyekto
Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.
Measure and value
Gawain 1 · 30 min
Ang pag-remeasure ng Level 1 slab para sa paniningil
- Ang gagawin mo
- Net quantities for the Level 1 slab
- Dokumento
- Bill lines 3.1 to 3.4
- Sa ERP
- Bill of Quantities
Measure and value
Gawain 2 · 25 min
Ang pag-price ng bill at pag-value ng trade hanggang sa kasalukuyan
- Ang gagawin mo
- The concrete structure trade to date
- Dokumento
- Priced bill against the draft claim
- Sa ERP
- Bill of Quantities
The change
Gawain 3 · 25 min
Presyuhan ang thickening ng slab bilang variation
- Ang gagawin mo
- Variation 14 (the priced change)
- Dokumento
- Site instruction 14
- Sa ERP
- Variations
The claim
Gawain 4 · 30 min
Payment claim 7 para sa named month
- Ang gagawin mo
- Payment claim 7 with GST
- Dokumento
- Schedule of values, claims 1 to 6
- Sa ERP
- Contracts, Progress Claims
The claim
Gawain 5 · 25 min
Retention, retention cap, at ang halagang talagang babayaran
- Ang gagawin mo
- Retention and the amount payable
- Dokumento
- Annexure Part A
- Sa ERP
- Contracts, Progress Claims
The clock
Gawain 6 · 25 min
Ang iskedyul ng bayad at ang statutory clock
- Ang gagawin mo
- The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
- Dokumento
- The payment schedule
- Sa ERP
- Progress Claims
How a measured slab becomes a payment
Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.