OpenConstruction Academy
Mag-sign in / Magrehistro
FIL

Panimula ng kurso · 3 min

I-remeasure, mag-claim, at mabayaran (Australia, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Simulan ang gawain 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Kathang-isip na proyekto
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Trabaho sa ERP
6 gawain, mga 2 oras 40 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • Site managerYour firm, on site
    • Draft claim 7Gawain 2
  • SuperintendentAssesses the claim
    • Site instruction 14Gawain 3
    • Payment scheduleGawain 6
  • Commercial managerYour firm
    • Annexure termsGawain 5
IkawQuantity surveyor, head contractor

Lumalabas sa iyo

    • Payment claim 7Gawain 4
    • Amount payableGawain 5
    PrincipalPays the claim
    • Last day to applyGawain 6
    AdjudicatorUnder the NSW Act

Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.

Ang ruta mo sa proyekto

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Gawain 1 · 30 min

    Ang pag-remeasure ng Level 1 slab para sa paniningil

    Ang gagawin mo
    Net quantities for the Level 1 slab
    Dokumento
    Bill lines 3.1 to 3.4
    Sa ERP
    Bill of Quantities
  2. Measure and value

    Gawain 2 · 25 min

    Ang pag-price ng bill at pag-value ng trade hanggang sa kasalukuyan

    Ang gagawin mo
    The concrete structure trade to date
    Dokumento
    Priced bill against the draft claim
    Sa ERP
    Bill of Quantities
  3. The change

    Gawain 3 · 25 min

    Presyuhan ang thickening ng slab bilang variation

    Ang gagawin mo
    Variation 14 (the priced change)
    Dokumento
    Site instruction 14
    Sa ERP
    Variations
  4. The claim

    Gawain 4 · 30 min

    Payment claim 7 para sa named month

    Ang gagawin mo
    Payment claim 7 with GST
    Dokumento
    Schedule of values, claims 1 to 6
    Sa ERP
    Contracts, Progress Claims
  5. The claim

    Gawain 5 · 25 min

    Retention, retention cap, at ang halagang talagang babayaran

    Ang gagawin mo
    Retention and the amount payable
    Dokumento
    Annexure Part A
    Sa ERP
    Contracts, Progress Claims
  6. The clock

    Gawain 6 · 25 min

    Ang iskedyul ng bayad at ang statutory clock

    Ang gagawin mo
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Dokumento
    The payment schedule
    Sa ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Gawain 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Gawain 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Gawain 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Gawain 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.