Remăsurare, cerere de plată și încasare (Australia, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Începe sarcina 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Proiect fictiv
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Lucru în ERP
6 sarcini, circa 2 h 40 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Site managerYour firm, on site
    • Draft claim 7Sarcina 2
  • SuperintendentAssesses the claim
    • Site instruction 14Sarcina 3
    • Payment scheduleSarcina 6
  • Commercial managerYour firm
    • Annexure termsSarcina 5
TuQuantity surveyor, head contractor

Pleacă de la tine

    • Payment claim 7Sarcina 4
    • Amount payableSarcina 5
    PrincipalPays the claim
    • Last day to applySarcina 6
    AdjudicatorUnder the NSW Act

Proiectul și persoanele sunt fictive. Portretele sunt generate.

Traseul tău prin proiect

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Sarcina 1 · 30 min

    Remăsurați placa Nivelului 1 pentru revendicare

    Produci
    Net quantities for the Level 1 slab
    Document
    Bill lines 3.1 to 3.4
    În ERP
    Bill of Quantities
  2. Measure and value

    Sarcina 2 · 25 min

    Stabiliți prețul listei și evaluați meseria până la data curentă

    Produci
    The concrete structure trade to date
    Document
    Priced bill against the draft claim
    În ERP
    Bill of Quantities
  3. The change

    Sarcina 3 · 25 min

    Evaluarea îngroșării plăcii ca variație

    Produci
    Variation 14 (the priced change)
    Document
    Site instruction 14
    În ERP
    Variations
  4. The claim

    Sarcina 4 · 30 min

    Revendicarea de plată 7 pentru luna numită

    Produci
    Payment claim 7 with GST
    Document
    Schedule of values, claims 1 to 6
    În ERP
    Contracts, Progress Claims
  5. The claim

    Sarcina 5 · 25 min

    Retenția, garanția și ce este efectiv de plătit

    Produci
    Retention and the amount payable
    Document
    Annexure Part A
    În ERP
    Contracts, Progress Claims
  6. The clock

    Sarcina 6 · 25 min

    Notificarea de plată și ceasul legal

    Produci
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Document
    The payment schedule
    În ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Sarcina 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Sarcina 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Sarcina 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Sarcina 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.