Course introduction · 3 min

Remeasure, claim and get paid (Australia, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Start task 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Fictional project
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Work in the ERP
6 tasks, about 2 h 40 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Site managerYour firm, on site
    • Draft claim 7Task 2
  • SuperintendentAssesses the claim
    • Site instruction 14Task 3
    • Payment scheduleTask 6
  • Commercial managerYour firm
    • Annexure termsTask 5
YouQuantity surveyor, head contractor

Goes from you

    • Payment claim 7Task 4
    • Amount payableTask 5
    PrincipalPays the claim
    • Last day to applyTask 6
    AdjudicatorUnder the NSW Act

The project and the people are fictional. Portraits are generated.

Your route through the job

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Task 1 · 30 min

    Remeasure the Level 1 slab for the claim

    You produce
    Net quantities for the Level 1 slab
    Document
    Bill lines 3.1 to 3.4
    In the ERP
    Bill of Quantities
  2. Measure and value

    Task 2 · 25 min

    Price the bill and value the trade to date

    You produce
    The concrete structure trade to date
    Document
    Priced bill against the draft claim
    In the ERP
    Bill of Quantities
  3. The change

    Task 3 · 25 min

    Value the slab thickening as a variation

    You produce
    Variation 14 (the priced change)
    Document
    Site instruction 14
    In the ERP
    Variations
  4. The claim

    Task 4 · 30 min

    Payment claim 7 for the named month

    You produce
    Payment claim 7 with GST
    Document
    Schedule of values, claims 1 to 6
    In the ERP
    Contracts, Progress Claims
  5. The claim

    Task 5 · 25 min

    Retention, security and what is actually payable

    You produce
    Retention and the amount payable
    Document
    Annexure Part A
    In the ERP
    Contracts, Progress Claims
  6. The clock

    Task 6 · 25 min

    The payment schedule and the statutory clock

    You produce
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Document
    The payment schedule
    In the ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Task 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Task 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Task 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Task 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Blue is what the task adds; grey is carried over from before.

In short. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.