Course introduction · 3 min
Remeasure, claim and get paid (Australia, AS 4000)
You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.
Fictional project- Building
- Two-storey outpatient clinic, Class 9a, concrete frame
- Contract
- AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
- Story
- November 2026 to January 2027
- Work in the ERP
- 6 tasks, about 2 h 40 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Site managerYour firm, on site
- Draft claim 7Task 2
- SuperintendentAssesses the claim
- Site instruction 14Task 3
- Payment scheduleTask 6
Commercial managerYour firm- Annexure termsTask 5
YouQuantity surveyor, head contractorGoes from you
- Payment claim 7Task 4
- Amount payableTask 5
- Last day to applyTask 6
The project and the people are fictional. Portraits are generated.
Your route through the job
Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.
Measure and value
Task 1 · 30 min
Remeasure the Level 1 slab for the claim
- You produce
- Net quantities for the Level 1 slab
- Document
- Bill lines 3.1 to 3.4
- In the ERP
- Bill of Quantities
Measure and value
Task 2 · 25 min
Price the bill and value the trade to date
- You produce
- The concrete structure trade to date
- Document
- Priced bill against the draft claim
- In the ERP
- Bill of Quantities
The change
Task 3 · 25 min
Value the slab thickening as a variation
- You produce
- Variation 14 (the priced change)
- Document
- Site instruction 14
- In the ERP
- Variations
The claim
Task 4 · 30 min
Payment claim 7 for the named month
- You produce
- Payment claim 7 with GST
- Document
- Schedule of values, claims 1 to 6
- In the ERP
- Contracts, Progress Claims
The claim
Task 5 · 25 min
Retention, security and what is actually payable
- You produce
- Retention and the amount payable
- Document
- Annexure Part A
- In the ERP
- Contracts, Progress Claims
The clock
Task 6 · 25 min
The payment schedule and the statutory clock
- You produce
- The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
- Document
- The payment schedule
- In the ERP
- Progress Claims
How a measured slab becomes a payment
Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.
Blue is what the task adds; grey is carried over from before.
In short. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.