OpenConstruction Academy
Logi sisse / Registreeru
ET

Kursuse sissejuhatus · 3 min

Ülemõõtmine, nõue ja tasu kättesaamine (Austraalia, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Alusta ülesannet 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Väljamõeldud projekt
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Töö ERP-s
Ülesandeid 6, umbes 2 h 40 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • Site managerYour firm, on site
    • Draft claim 7Ülesanne 2
  • SuperintendentAssesses the claim
    • Site instruction 14Ülesanne 3
    • Payment scheduleÜlesanne 6
  • Commercial managerYour firm
    • Annexure termsÜlesanne 5
SinaQuantity surveyor, head contractor

Läheb sinult

    • Payment claim 7Ülesanne 4
    • Amount payableÜlesanne 5
    PrincipalPays the claim
    • Last day to applyÜlesanne 6
    AdjudicatorUnder the NSW Act

Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.

Sinu tee läbi projekti

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Ülesanne 1 · 30 min

    1. tasandi plaadi ümbermõõtmine nõude jaoks

    Sinu tulemus
    Net quantities for the Level 1 slab
    Dokument
    Bill lines 3.1 to 3.4
    ERP-s
    Bill of Quantities
  2. Measure and value

    Ülesanne 2 · 25 min

    Eelarve hinnastamine ja rea väärtustamine tähtpäeval

    Sinu tulemus
    The concrete structure trade to date
    Dokument
    Priced bill against the draft claim
    ERP-s
    Bill of Quantities
  3. The change

    Ülesanne 3 · 25 min

    Plaadi paksendamise hinnastamine muudatusena

    Sinu tulemus
    Variation 14 (the priced change)
    Dokument
    Site instruction 14
    ERP-s
    Variations
  4. The claim

    Ülesanne 4 · 30 min

    Maksenõue 7 nimetatud kuu jaoks

    Sinu tulemus
    Payment claim 7 with GST
    Dokument
    Schedule of values, claims 1 to 6
    ERP-s
    Contracts, Progress Claims
  5. The claim

    Ülesanne 5 · 25 min

    Kinnipidamine, kinnipidamise ülempiir ja tegelikult makstav summa

    Sinu tulemus
    Retention and the amount payable
    Dokument
    Annexure Part A
    ERP-s
    Contracts, Progress Claims
  6. The clock

    Ülesanne 6 · 25 min

    Maksekinnitus ja seaduslik kell

    Sinu tulemus
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Dokument
    The payment schedule
    ERP-s
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Ülesanne 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Ülesanne 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Ülesanne 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Ülesanne 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.