Ülemõõtmine, nõue ja tasu kättesaamine (Austraalia, AS 4000)
You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.
Väljamõeldud projekt- Building
- Two-storey outpatient clinic, Class 9a, concrete frame
- Contract
- AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
- Story
- November 2026 to January 2027
- Töö ERP-s
- Ülesandeid 6, umbes 2 h 40 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- Site managerYour firm, on site
- Draft claim 7Ülesanne 2
- SuperintendentAssesses the claim
- Site instruction 14Ülesanne 3
- Payment scheduleÜlesanne 6
Commercial managerYour firm- Annexure termsÜlesanne 5
SinaQuantity surveyor, head contractorLäheb sinult
- Payment claim 7Ülesanne 4
- Amount payableÜlesanne 5
- Last day to applyÜlesanne 6
Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.
Sinu tee läbi projekti
Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.
Measure and value
Ülesanne 1 · 30 min
1. tasandi plaadi ümbermõõtmine nõude jaoks
- Sinu tulemus
- Net quantities for the Level 1 slab
- Dokument
- Bill lines 3.1 to 3.4
- ERP-s
- Bill of Quantities
Measure and value
Ülesanne 2 · 25 min
Eelarve hinnastamine ja rea väärtustamine tähtpäeval
- Sinu tulemus
- The concrete structure trade to date
- Dokument
- Priced bill against the draft claim
- ERP-s
- Bill of Quantities
The change
Ülesanne 3 · 25 min
Plaadi paksendamise hinnastamine muudatusena
- Sinu tulemus
- Variation 14 (the priced change)
- Dokument
- Site instruction 14
- ERP-s
- Variations
The claim
Ülesanne 4 · 30 min
Maksenõue 7 nimetatud kuu jaoks
- Sinu tulemus
- Payment claim 7 with GST
- Dokument
- Schedule of values, claims 1 to 6
- ERP-s
- Contracts, Progress Claims
The claim
Ülesanne 5 · 25 min
Kinnipidamine, kinnipidamise ülempiir ja tegelikult makstav summa
- Sinu tulemus
- Retention and the amount payable
- Dokument
- Annexure Part A
- ERP-s
- Contracts, Progress Claims
The clock
Ülesanne 6 · 25 min
Maksekinnitus ja seaduslik kell
- Sinu tulemus
- The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
- Dokument
- The payment schedule
- ERP-s
- Progress Claims
How a measured slab becomes a payment
Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.