Introduktion til kurset · 3 min
Genopmåle, kræve og blive betalt (Australien, AS 4000)
You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.
Fiktivt projekt- Building
- Two-storey outpatient clinic, Class 9a, concrete frame
- Contract
- AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
- Story
- November 2026 to January 2027
- Arbejde i ERP
- 6 opgaver, cirka 2 t 40 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Site managerYour firm, on site
- Draft claim 7Opgave 2
- SuperintendentAssesses the claim
- Site instruction 14Opgave 3
- Payment scheduleOpgave 6
Commercial managerYour firm- Annexure termsOpgave 5
DigQuantity surveyor, head contractorGår fra dig
- Payment claim 7Opgave 4
- Amount payableOpgave 5
- Last day to applyOpgave 6
Projektet og personerne er fiktive. Portrætterne er genererede.
Din vej gennem sagen
Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.
Measure and value
Opgave 1 · 30 min
Genopmål Level 1-pladen til kravet
- Du leverer
- Net quantities for the Level 1 slab
- Dokument
- Bill lines 3.1 to 3.4
- I ERP
- Bill of Quantities
Measure and value
Opgave 2 · 25 min
Prissæt listen og værdisæt faget til dato
- Du leverer
- The concrete structure trade to date
- Dokument
- Priced bill against the draft claim
- I ERP
- Bill of Quantities
The change
Opgave 3 · 25 min
Værdisæt pladefortykningen som en ændring
- Du leverer
- Variation 14 (the priced change)
- Dokument
- Site instruction 14
- I ERP
- Variations
The claim
Opgave 4 · 30 min
Betalingskrav 7 for den navngivne måned
- Du leverer
- Payment claim 7 with GST
- Dokument
- Schedule of values, claims 1 to 6
- I ERP
- Contracts, Progress Claims
The claim
Opgave 5 · 25 min
Tilbageholdelse, sikkerhed og hvad der faktisk skal betales
- Du leverer
- Retention and the amount payable
- Dokument
- Annexure Part A
- I ERP
- Contracts, Progress Claims
The clock
Opgave 6 · 25 min
Betalingsopgørelsen og det lovbestemte ur
- Du leverer
- The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
- Dokument
- The payment schedule
- I ERP
- Progress Claims
How a measured slab becomes a payment
Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.