Genopmåle, kræve og blive betalt (Australien, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Start opgave 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Fiktivt projekt
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Arbejde i ERP
6 opgaver, cirka 2 t 40 min

Hvem giver hvad til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til dig

  • Site managerYour firm, on site
    • Draft claim 7Opgave 2
  • SuperintendentAssesses the claim
    • Site instruction 14Opgave 3
    • Payment scheduleOpgave 6
  • Commercial managerYour firm
    • Annexure termsOpgave 5
DigQuantity surveyor, head contractor

Går fra dig

    • Payment claim 7Opgave 4
    • Amount payableOpgave 5
    PrincipalPays the claim
    • Last day to applyOpgave 6
    AdjudicatorUnder the NSW Act

Projektet og personerne er fiktive. Portrætterne er genererede.

Din vej gennem sagen

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Opgave 1 · 30 min

    Genopmål Level 1-pladen til kravet

    Du leverer
    Net quantities for the Level 1 slab
    Dokument
    Bill lines 3.1 to 3.4
    I ERP
    Bill of Quantities
  2. Measure and value

    Opgave 2 · 25 min

    Prissæt listen og værdisæt faget til dato

    Du leverer
    The concrete structure trade to date
    Dokument
    Priced bill against the draft claim
    I ERP
    Bill of Quantities
  3. The change

    Opgave 3 · 25 min

    Værdisæt pladefortykningen som en ændring

    Du leverer
    Variation 14 (the priced change)
    Dokument
    Site instruction 14
    I ERP
    Variations
  4. The claim

    Opgave 4 · 30 min

    Betalingskrav 7 for den navngivne måned

    Du leverer
    Payment claim 7 with GST
    Dokument
    Schedule of values, claims 1 to 6
    I ERP
    Contracts, Progress Claims
  5. The claim

    Opgave 5 · 25 min

    Tilbageholdelse, sikkerhed og hvad der faktisk skal betales

    Du leverer
    Retention and the amount payable
    Dokument
    Annexure Part A
    I ERP
    Contracts, Progress Claims
  6. The clock

    Opgave 6 · 25 min

    Betalingsopgørelsen og det lovbestemte ur

    Du leverer
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Dokument
    The payment schedule
    I ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Opgave 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Opgave 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Opgave 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Opgave 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Blå er det, opgaven tilføjer; grå er overført fra før.

Kort sagt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.