Introduktion till kursen · 3 min
Mäta om, begära betalning och bli betald (Australien, AS 4000)
You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.
Fiktivt projekt- Building
- Two-storey outpatient clinic, Class 9a, concrete frame
- Contract
- AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
- Story
- November 2026 to January 2027
- Arbete i ERP
- 6 uppgifter, cirka 2 h 40 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Site managerYour firm, on site
- Draft claim 7Uppgift 2
- SuperintendentAssesses the claim
- Site instruction 14Uppgift 3
- Payment scheduleUppgift 6
Commercial managerYour firm- Annexure termsUppgift 5
DuQuantity surveyor, head contractorGår från dig
- Payment claim 7Uppgift 4
- Amount payableUppgift 5
- Last day to applyUppgift 6
Projektet och personerna är fiktiva. Porträtten är genererade.
Din väg genom projektet
Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.
Measure and value
Uppgift 1 · 30 min
Att mäta om plattan på nivå 1 för ansökan
- Du tar fram
- Net quantities for the Level 1 slab
- Dokument
- Bill lines 3.1 to 3.4
- I ERP
- Bill of Quantities
Measure and value
Uppgift 2 · 25 min
Att prissätta mängdförteckningen och värdera posten vid ett datum
- Du tar fram
- The concrete structure trade to date
- Dokument
- Priced bill against the draft claim
- I ERP
- Bill of Quantities
The change
Uppgift 3 · 25 min
Att prissätta plattans förtjockning som en ändring
- Du tar fram
- Variation 14 (the priced change)
- Dokument
- Site instruction 14
- I ERP
- Variations
The claim
Uppgift 4 · 30 min
Betalningsansökan 7 för den namngivna månaden
- Du tar fram
- Payment claim 7 with GST
- Dokument
- Schedule of values, claims 1 to 6
- I ERP
- Contracts, Progress Claims
The claim
Uppgift 5 · 25 min
Garantiavdrag, garanti och det belopp som faktiskt ska betalas
- Du tar fram
- Retention and the amount payable
- Dokument
- Annexure Part A
- I ERP
- Contracts, Progress Claims
The clock
Uppgift 6 · 25 min
Betalningsbeskedet och den lagstadgade klockan
- Du tar fram
- The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
- Dokument
- The payment schedule
- I ERP
- Progress Claims
How a measured slab becomes a payment
Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.