OpenConstruction Academy
Logga in / Registrera
SV

Introduktion till kursen · 3 min

Mäta om, begära betalning och bli betald (Australien, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Starta uppgift 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Fiktivt projekt
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Arbete i ERP
6 uppgifter, cirka 2 h 40 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Site managerYour firm, on site
    • Draft claim 7Uppgift 2
  • SuperintendentAssesses the claim
    • Site instruction 14Uppgift 3
    • Payment scheduleUppgift 6
  • Commercial managerYour firm
    • Annexure termsUppgift 5
DuQuantity surveyor, head contractor

Går från dig

    • Payment claim 7Uppgift 4
    • Amount payableUppgift 5
    PrincipalPays the claim
    • Last day to applyUppgift 6
    AdjudicatorUnder the NSW Act

Projektet och personerna är fiktiva. Porträtten är genererade.

Din väg genom projektet

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Uppgift 1 · 30 min

    Att mäta om plattan på nivå 1 för ansökan

    Du tar fram
    Net quantities for the Level 1 slab
    Dokument
    Bill lines 3.1 to 3.4
    I ERP
    Bill of Quantities
  2. Measure and value

    Uppgift 2 · 25 min

    Att prissätta mängdförteckningen och värdera posten vid ett datum

    Du tar fram
    The concrete structure trade to date
    Dokument
    Priced bill against the draft claim
    I ERP
    Bill of Quantities
  3. The change

    Uppgift 3 · 25 min

    Att prissätta plattans förtjockning som en ändring

    Du tar fram
    Variation 14 (the priced change)
    Dokument
    Site instruction 14
    I ERP
    Variations
  4. The claim

    Uppgift 4 · 30 min

    Betalningsansökan 7 för den namngivna månaden

    Du tar fram
    Payment claim 7 with GST
    Dokument
    Schedule of values, claims 1 to 6
    I ERP
    Contracts, Progress Claims
  5. The claim

    Uppgift 5 · 25 min

    Garantiavdrag, garanti och det belopp som faktiskt ska betalas

    Du tar fram
    Retention and the amount payable
    Dokument
    Annexure Part A
    I ERP
    Contracts, Progress Claims
  6. The clock

    Uppgift 6 · 25 min

    Betalningsbeskedet och den lagstadgade klockan

    Du tar fram
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Dokument
    The payment schedule
    I ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Uppgift 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Uppgift 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Uppgift 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Uppgift 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.