Måle opp på nytt, kreve og bli betalt (Australia, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Start oppgave 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Fiktivt prosjekt
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Arbeid i ERP
6 oppgaver, omtrent 2 t 40 min

Hvem gir hva til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til deg

  • Site managerYour firm, on site
    • Draft claim 7Oppgave 2
  • SuperintendentAssesses the claim
    • Site instruction 14Oppgave 3
    • Payment scheduleOppgave 6
  • Commercial managerYour firm
    • Annexure termsOppgave 5
DuQuantity surveyor, head contractor

Går fra deg

    • Payment claim 7Oppgave 4
    • Amount payableOppgave 5
    PrincipalPays the claim
    • Last day to applyOppgave 6
    AdjudicatorUnder the NSW Act

Prosjektet og personene er fiktive. Portrettene er genererte.

Din vei gjennom prosjektet

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Oppgave 1 · 30 min

    Mål opp dekket på nivå 1 på nytt for kravet

    Du leverer
    Net quantities for the Level 1 slab
    Dokument
    Bill lines 3.1 to 3.4
    I ERP
    Bill of Quantities
  2. Measure and value

    Oppgave 2 · 25 min

    Prissett Billen og verdisett faget til dags dato

    Du leverer
    The concrete structure trade to date
    Dokument
    Priced bill against the draft claim
    I ERP
    Bill of Quantities
  3. The change

    Oppgave 3 · 25 min

    Verdisett dekkefortykningen som en endring

    Du leverer
    Variation 14 (the priced change)
    Dokument
    Site instruction 14
    I ERP
    Variations
  4. The claim

    Oppgave 4 · 30 min

    Betalingskrav 7 for den navngitte måneden

    Du leverer
    Payment claim 7 with GST
    Dokument
    Schedule of values, claims 1 to 6
    I ERP
    Contracts, Progress Claims
  5. The claim

    Oppgave 5 · 25 min

    Tilbakehold, sikkerhet og det som faktisk skal betales

    Du leverer
    Retention and the amount payable
    Dokument
    Annexure Part A
    I ERP
    Contracts, Progress Claims
  6. The clock

    Oppgave 6 · 25 min

    Betalingsplanen og det lovbestemte klokkeslettet

    Du leverer
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Dokument
    The payment schedule
    I ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Oppgave 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Oppgave 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Oppgave 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Oppgave 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Blått er det oppgaven legger til; grått er overført fra før.

Kort sagt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.