Introduksjon til kurset · 3 min
Måle opp på nytt, kreve og bli betalt (Australia, AS 4000)
You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.
Fiktivt prosjekt- Building
- Two-storey outpatient clinic, Class 9a, concrete frame
- Contract
- AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
- Story
- November 2026 to January 2027
- Arbeid i ERP
- 6 oppgaver, omtrent 2 t 40 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- Site managerYour firm, on site
- Draft claim 7Oppgave 2
- SuperintendentAssesses the claim
- Site instruction 14Oppgave 3
- Payment scheduleOppgave 6
Commercial managerYour firm- Annexure termsOppgave 5
DuQuantity surveyor, head contractorGår fra deg
- Payment claim 7Oppgave 4
- Amount payableOppgave 5
- Last day to applyOppgave 6
Prosjektet og personene er fiktive. Portrettene er genererte.
Din vei gjennom prosjektet
Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.
Measure and value
Oppgave 1 · 30 min
Mål opp dekket på nivå 1 på nytt for kravet
- Du leverer
- Net quantities for the Level 1 slab
- Dokument
- Bill lines 3.1 to 3.4
- I ERP
- Bill of Quantities
Measure and value
Oppgave 2 · 25 min
Prissett Billen og verdisett faget til dags dato
- Du leverer
- The concrete structure trade to date
- Dokument
- Priced bill against the draft claim
- I ERP
- Bill of Quantities
The change
Oppgave 3 · 25 min
Verdisett dekkefortykningen som en endring
- Du leverer
- Variation 14 (the priced change)
- Dokument
- Site instruction 14
- I ERP
- Variations
The claim
Oppgave 4 · 30 min
Betalingskrav 7 for den navngitte måneden
- Du leverer
- Payment claim 7 with GST
- Dokument
- Schedule of values, claims 1 to 6
- I ERP
- Contracts, Progress Claims
The claim
Oppgave 5 · 25 min
Tilbakehold, sikkerhet og det som faktisk skal betales
- Du leverer
- Retention and the amount payable
- Dokument
- Annexure Part A
- I ERP
- Contracts, Progress Claims
The clock
Oppgave 6 · 25 min
Betalingsplanen og det lovbestemte klokkeslettet
- Du leverer
- The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
- Dokument
- The payment schedule
- I ERP
- Progress Claims
How a measured slab becomes a payment
Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.