Uvod u tečaj · 3 min
Obračun, zahtjev i naplata (Australija, AS 4000)
You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.
Izmišljeni projekt- Building
- Two-storey outpatient clinic, Class 9a, concrete frame
- Contract
- AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
- Story
- November 2026 to January 2027
- Rad u ERP-u
- Zadataka: 6, oko 2 h 40 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Site managerYour firm, on site
- Draft claim 7Zadatak 2
- SuperintendentAssesses the claim
- Site instruction 14Zadatak 3
- Payment scheduleZadatak 6
Commercial managerYour firm- Annexure termsZadatak 5
ViQuantity surveyor, head contractorOdlazi od vas
- Payment claim 7Zadatak 4
- Amount payableZadatak 5
- Last day to applyZadatak 6
Projekt i osobe su izmišljeni. Portreti su generirani.
Vaš put kroz projekt
Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.
Measure and value
Zadatak 1 · 30 min
Ponovno mjerenje ploče 1. razine za situaciju
- Vaš rezultat
- Net quantities for the Level 1 slab
- Dokument
- Bill lines 3.1 to 3.4
- U ERP-u
- Bill of Quantities
Measure and value
Zadatak 2 · 25 min
Cijenjenje troškovnika i vrednovanje stavke na datum
- Vaš rezultat
- The concrete structure trade to date
- Dokument
- Priced bill against the draft claim
- U ERP-u
- Bill of Quantities
The change
Zadatak 3 · 25 min
Cijenjenje podebljanja ploče kao izmjene
- Vaš rezultat
- Variation 14 (the priced change)
- Dokument
- Site instruction 14
- U ERP-u
- Variations
The claim
Zadatak 4 · 30 min
Situacija 7 za navedeni mjesec
- Vaš rezultat
- Payment claim 7 with GST
- Dokument
- Schedule of values, claims 1 to 6
- U ERP-u
- Contracts, Progress Claims
The claim
Zadatak 5 · 25 min
Osiguranje, gornja granica osiguranja, i iznos koji se stvarno plaća
- Vaš rezultat
- Retention and the amount payable
- Dokument
- Annexure Part A
- U ERP-u
- Contracts, Progress Claims
The clock
Zadatak 6 · 25 min
Raspored plaćanja i zakonski rok
- Vaš rezultat
- The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
- Dokument
- The payment schedule
- U ERP-u
- Progress Claims
How a measured slab becomes a payment
Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.