Uvod u tečaj · 3 min

Obračun, zahtjev i naplata (Australija, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Započni zadatak 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Izmišljeni projekt
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Rad u ERP-u
Zadataka: 6, oko 2 h 40 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • Site managerYour firm, on site
    • Draft claim 7Zadatak 2
  • SuperintendentAssesses the claim
    • Site instruction 14Zadatak 3
    • Payment scheduleZadatak 6
  • Commercial managerYour firm
    • Annexure termsZadatak 5
ViQuantity surveyor, head contractor

Odlazi od vas

    • Payment claim 7Zadatak 4
    • Amount payableZadatak 5
    PrincipalPays the claim
    • Last day to applyZadatak 6
    AdjudicatorUnder the NSW Act

Projekt i osobe su izmišljeni. Portreti su generirani.

Vaš put kroz projekt

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Zadatak 1 · 30 min

    Ponovno mjerenje ploče 1. razine za situaciju

    Vaš rezultat
    Net quantities for the Level 1 slab
    Dokument
    Bill lines 3.1 to 3.4
    U ERP-u
    Bill of Quantities
  2. Measure and value

    Zadatak 2 · 25 min

    Cijenjenje troškovnika i vrednovanje stavke na datum

    Vaš rezultat
    The concrete structure trade to date
    Dokument
    Priced bill against the draft claim
    U ERP-u
    Bill of Quantities
  3. The change

    Zadatak 3 · 25 min

    Cijenjenje podebljanja ploče kao izmjene

    Vaš rezultat
    Variation 14 (the priced change)
    Dokument
    Site instruction 14
    U ERP-u
    Variations
  4. The claim

    Zadatak 4 · 30 min

    Situacija 7 za navedeni mjesec

    Vaš rezultat
    Payment claim 7 with GST
    Dokument
    Schedule of values, claims 1 to 6
    U ERP-u
    Contracts, Progress Claims
  5. The claim

    Zadatak 5 · 25 min

    Osiguranje, gornja granica osiguranja, i iznos koji se stvarno plaća

    Vaš rezultat
    Retention and the amount payable
    Dokument
    Annexure Part A
    U ERP-u
    Contracts, Progress Claims
  6. The clock

    Zadatak 6 · 25 min

    Raspored plaćanja i zakonski rok

    Vaš rezultat
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Dokument
    The payment schedule
    U ERP-u
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Zadatak 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Zadatak 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Zadatak 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Zadatak 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.