Inleiding tot de cursus · 3 min

Hermeten, claimen en betaald krijgen (Australië, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Start opdracht 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Fictief project
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Werk in de ERP
6 opdrachten, ongeveer 2 u 40 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • Site managerYour firm, on site
    • Draft claim 7Opdracht 2
  • SuperintendentAssesses the claim
    • Site instruction 14Opdracht 3
    • Payment scheduleOpdracht 6
  • Commercial managerYour firm
    • Annexure termsOpdracht 5
UQuantity surveyor, head contractor

Gaat van u uit

    • Payment claim 7Opdracht 4
    • Amount payableOpdracht 5
    PrincipalPays the claim
    • Last day to applyOpdracht 6
    AdjudicatorUnder the NSW Act

Het project en de mensen zijn fictief. De portretten zijn gegenereerd.

Uw route door het project

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Opdracht 1 · 30 min

    Hermeet de vloerplaat van niveau 1 voor de claim

    U levert
    Net quantities for the Level 1 slab
    Document
    Bill lines 3.1 to 3.4
    In de ERP
    Bill of Quantities
  2. Measure and value

    Opdracht 2 · 25 min

    Prijs het bestek en waardeer de post tot nu toe

    U levert
    The concrete structure trade to date
    Document
    Priced bill against the draft claim
    In de ERP
    Bill of Quantities
  3. The change

    Opdracht 3 · 25 min

    Waardeer de verdikking van de vloerplaat als een wijziging

    U levert
    Variation 14 (the priced change)
    Document
    Site instruction 14
    In de ERP
    Variations
  4. The claim

    Opdracht 4 · 30 min

    Betalingsclaim 7 voor de genoemde maand

    U levert
    Payment claim 7 with GST
    Document
    Schedule of values, claims 1 to 6
    In de ERP
    Contracts, Progress Claims
  5. The claim

    Opdracht 5 · 25 min

    Inhouding, zekerheid en wat werkelijk betaalbaar is

    U levert
    Retention and the amount payable
    Document
    Annexure Part A
    In de ERP
    Contracts, Progress Claims
  6. The clock

    Opdracht 6 · 25 min

    Het betalingsschema en de wettelijke klok

    U levert
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Document
    The payment schedule
    In de ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Opdracht 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Opdracht 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Opdracht 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Opdracht 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.