Úvod do kurzu · 3 min

Přeměření, nárok a získání platby (Austrálie, AS 4000)

You are the quantity surveyor (QS) of the head contractor building a community health centre in New South Wales: you measure the work and claim payment for it. In six tasks you take Stage 2 from a remeasured floor slab to payment claim 7, the monthly bill to the client, then the retention held back on it and the legal clock that starts when the claim is served.

Začít úlohu 1

A two-storey brick building wrapped in scaffolding on a flat, open site, with workers in high-visibility vests to the right.Smyšlený projekt
Yarrabinda Community Health CentreStage 2, two-storey outpatient clinic, New South Wales
Building
Two-storey outpatient clinic, Class 9a, concrete frame
Contract
AS 4000-1997, the standard Australian contract, at a fixed price with a priced bill of quantities
Story
November 2026 to January 2027
Práce v ERP
Úlohy: 6, asi 2 h 40 min

Kdo komu co předává

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Přichází k vám

  • Site managerYour firm, on site
    • Draft claim 7Úloha 2
  • SuperintendentAssesses the claim
    • Site instruction 14Úloha 3
    • Payment scheduleÚloha 6
  • Commercial managerYour firm
    • Annexure termsÚloha 5
VyQuantity surveyor, head contractor

Odchází od vás

    • Payment claim 7Úloha 4
    • Amount payableÚloha 5
    PrincipalPays the claim
    • Last day to applyÚloha 6
    AdjudicatorUnder the NSW Act

Projekt i lidé jsou smyšlení. Portréty jsou vygenerované.

Vaše cesta zakázkou

Two tasks to measure and value the slab, one for the change, two to build and settle the claim, one on the legal clock. Start with task 1: in the Bill of Quantities you measure the net quantities of the Level 1 slab.

  1. Measure and value

    Úloha 1 · 30 min

    Přeměřte desku úrovně 1 pro nárok

    Výstup
    Net quantities for the Level 1 slab
    Dokument
    Bill lines 3.1 to 3.4
    V ERP
    Bill of Quantities
  2. Measure and value

    Úloha 2 · 25 min

    Oceňte výkaz a ohodnoťte obor k dnešnímu dni

    Výstup
    The concrete structure trade to date
    Dokument
    Priced bill against the draft claim
    V ERP
    Bill of Quantities
  3. The change

    Úloha 3 · 25 min

    Ohodnoťte ztluštění desky jako změnu

    Výstup
    Variation 14 (the priced change)
    Dokument
    Site instruction 14
    V ERP
    Variations
  4. The claim

    Úloha 4 · 30 min

    Nárok na platbu 7 za uvedený měsíc

    Výstup
    Payment claim 7 with GST
    Dokument
    Schedule of values, claims 1 to 6
    V ERP
    Contracts, Progress Claims
  5. The claim

    Úloha 5 · 25 min

    Zádržné, jistota a co je skutečně splatné

    Výstup
    Retention and the amount payable
    Dokument
    Annexure Part A
    V ERP
    Contracts, Progress Claims
  6. The clock

    Úloha 6 · 25 min

    Výkaz plateb a zákonné hodiny

    Výstup
    The shortfall and the deadline to apply for adjudication, a fast independent decision on the unpaid amount
    Dokument
    The payment schedule
    V ERP
    Progress Claims

How a measured slab becomes a payment

Each step below is one task, in the order the money moves. The last task does not change the money: it fixes the dates by which you must act on it.

Net slab
Úloha 1Net quantityWhat was built, measured to the bill preambles, the rules at the front of the bill.
Sections 1 and 2Section 3
Úloha 2Trade valueEvery section at bill rates, to date.
GSTVariation 14This claim
Úloha 4Claim 7To date, less what was certified, plus variations. GST on top.
GSTRetentionPaid now
Úloha 5PayableRetention, a share held back as security, comes off the value. GST stays on the full value.

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Measure net. Price at bill rates. Claim what is not yet certified. GST once, on the full value.