কোর্সের পরিচিতি · 3 মি

CPWD রীতিতে রেট বিশ্লেষণ (ভারত)

You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.

কাজ 1 শুরু করুন

A single-storey health centre in grey block with bamboo scaffolding on red earth, a concrete mixer, cement bags and a stack of blocks in front, two workers in orange vests walking by.কাল্পনিক প্রকল্প
Kesarwadi Primary Health CentreVillage health centre · walls and frame rising
Building
Single-storey primary health centre in a village
Contract
Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
Currency
Rupees, worked before GST
ERP-তে কাজ
4টি কাজ, প্রায় 2 ঘ 20 মি

কে কাকে কী দেয়

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

আপনার কাছে আসে

  • Site engineerSends the analysis sheets
    • Brickwork analysis sheet and two brick offersকাজ 1
    • RCC M25 sheet and bar bending scheduleকাজ 3
  • Two contractorsQuote line 2.1 their own way
    • Quote A and quote Bকাজ 2
আপনিEstimating engineer, detailed estimate

আপনার কাছ থেকে যায়

    • Brickwork rate per m³কাজ 1
    • Complete rate and the gap to quote Aকাজ 2
    • RCC rate and the reinforcement lineকাজ 3
    • Estimate totalকাজ 4
    Executive EngineerChecks your rates

প্রকল্পে আপনার পথ

Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.

  1. Analyse the work

    কাজ 1 · 35 মি

    গাথুনির কাজ: সাশ্রয়ী উৎস, তারপর প্রতি m3 খরচ

    আপনার ফল
    Cost of 10 m³ of brickwork from the cheaper brick source
    নথি
    Analysis sheet and two brick offers
    ERP-তে
    Bill of Quantities
  2. Analyse the work

    কাজ 2 · 30 মি

    CPWD দরের বিপরীতে দুজন ঠিকাদারের দরপত্র

    আপনার ফল
    The CPWD rate on line 2.1, and how far quote A sits below it
    নথি
    Two contractor quotes
    ERP-তে
    Bill of Quantities
  3. Concrete and the estimate

    কাজ 3 · 40 মি

    RCC M25: কনক্রিটের দরে কী কী অন্তর্ভুক্ত হবে

    আপনার ফল
    RCC M25 rate on line 2.2, reinforcement kept on line 1.3
    নথি
    RCC sheet and bar bending schedule (the list of every steel bar)
    ERP-তে
    Bill of Quantities
  4. Concrete and the estimate

    কাজ 4 · 35 মি

    শিডিউল আইটেমে কস্ট ইনডেক্সসহ, বিশ্লেষিত আইটেমে ছাড়া

    আপনার ফল
    The estimate total, Direct Cost
    নথি
    Schedule base rates and the station cost index
    ERP-তে
    Bill of Quantities

From an analysis sheet to an estimate

A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.

Mason, beldar, bhistiCarriage to siteMaterials
কাজ 1What the work consumesPer 10 m³: materials, carriage from the source to site, and labour at the day rates of the schedule. The cheaper source counts delivered, not at the gate.
Profit and overheadsWater chargesMason, beldar, bhistiCarriage to siteMaterials
কাজ 2Water, then profit and overheadsWater charges go on the cost first. The percentage for profit and overheads then goes on that sum, not on labour alone and not in one step.
Bars, paid on line 1.3Labour and mixerCement, sand, aggregate
কাজ 3What belongs in the concrete rateThe sheet lists the bars, but line 1.3 already pays reinforcement by weight. Leave them in the rate and they are paid twice.
Analysed items, no indexCost indexSchedule base rates
কাজ 4Index on schedule items onlySchedule items take base rate plus the station cost index. Rates analysed from market rates are already at site prices and take none.

নীল হলো কাজটি যা যোগ করে; ধূসর আগের ধাপ থেকে আসা।

সংক্ষেপে. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.