معرفی دوره · 3 دقیقه
تحلیل نرخ بر پایه رویه CPWD (هند)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
پروژهٔ خیالی- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- کار در ERP
- 4 تکلیف، حدود 2 ساعت 20 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
به شما میرسد
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersتکلیف 1
- RCC M25 sheet and bar bending scheduleتکلیف 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote Bتکلیف 2
از شما میرود
- Brickwork rate per m³تکلیف 1
- Complete rate and the gap to quote Aتکلیف 2
- RCC rate and the reinforcement lineتکلیف 3
- Estimate totalتکلیف 4
مسیر شما در پروژه
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
تکلیف 1 · 35 دقیقه
آجرکاری: منبع ارزانتر، سپس هزینه در هر m3
- خروجی شما
- Cost of 10 m³ of brickwork from the cheaper brick source
- سند
- Analysis sheet and two brick offers
- در ERP
- Bill of Quantities
Analyse the work
تکلیف 2 · 30 دقیقه
دو پیشنهاد قیمت پیمانکار در برابر نرخ CPWD
- خروجی شما
- The CPWD rate on line 2.1, and how far quote A sits below it
- سند
- Two contractor quotes
- در ERP
- Bill of Quantities
Concrete and the estimate
تکلیف 3 · 40 دقیقه
RCC M25: آنچه به نرخ بتن تعلق دارد
- خروجی شما
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- سند
- RCC sheet and bar bending schedule (the list of every steel bar)
- در ERP
- Bill of Quantities
Concrete and the estimate
تکلیف 4 · 35 دقیقه
ردیفهای فهرستبها با ضریب هزینه، ردیفهای تحلیلی بدون آن
- خروجی شما
- The estimate total, Direct Cost
- سند
- Schedule base rates and the station cost index
- در ERP
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.