Kursuse sissejuhatus · 3 min
Hinnaanalüüs CPWD praktika järgi (India)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Väljamõeldud projekt- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- Töö ERP-s
- Ülesandeid 4, umbes 2 h 20 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersÜlesanne 1
- RCC M25 sheet and bar bending scheduleÜlesanne 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote BÜlesanne 2
Läheb sinult
- Brickwork rate per m³Ülesanne 1
- Complete rate and the gap to quote AÜlesanne 2
- RCC rate and the reinforcement lineÜlesanne 3
- Estimate totalÜlesanne 4
Sinu tee läbi projekti
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
Ülesanne 1 · 35 min
Müüritis: odavam allikas, seejärel maksumus m3 kohta
- Sinu tulemus
- Cost of 10 m³ of brickwork from the cheaper brick source
- Dokument
- Analysis sheet and two brick offers
- ERP-s
- Bill of Quantities
Analyse the work
Ülesanne 2 · 30 min
Kaks töövõtja pakkumist CPWD hinna vastu
- Sinu tulemus
- The CPWD rate on line 2.1, and how far quote A sits below it
- Dokument
- Two contractor quotes
- ERP-s
- Bill of Quantities
Concrete and the estimate
Ülesanne 3 · 40 min
RCC M25: mis kuulub betooni hinda
- Sinu tulemus
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Dokument
- RCC sheet and bar bending schedule (the list of every steel bar)
- ERP-s
- Bill of Quantities
Concrete and the estimate
Ülesanne 4 · 35 min
Hinnakirja kirjed kuluindeksiga, analüüsitud kirjed ilma
- Sinu tulemus
- The estimate total, Direct Cost
- Dokument
- Schedule base rates and the station cost index
- ERP-s
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.