Inleiding tot de cursus · 3 min
Tarievenanalyse volgens de CPWD-praktijk (India)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Fictief project- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- Werk in de ERP
- 4 opdrachten, ongeveer 2 u 20 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersOpdracht 1
- RCC M25 sheet and bar bending scheduleOpdracht 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote BOpdracht 2
Gaat van u uit
- Brickwork rate per m³Opdracht 1
- Complete rate and the gap to quote AOpdracht 2
- RCC rate and the reinforcement lineOpdracht 3
- Estimate totalOpdracht 4
Uw route door het project
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
Opdracht 1 · 35 min
Metselwerk: de goedkopere bron, daarna de kosten per m3
- U levert
- Cost of 10 m³ of brickwork from the cheaper brick source
- Document
- Analysis sheet and two brick offers
- In de ERP
- Bill of Quantities
Analyse the work
Opdracht 2 · 30 min
Twee aannemersoffertes vergeleken met de CPWD-prijs
- U levert
- The CPWD rate on line 2.1, and how far quote A sits below it
- Document
- Two contractor quotes
- In de ERP
- Bill of Quantities
Concrete and the estimate
Opdracht 3 · 40 min
RCC M25: wat hoort in de betonprijs
- U levert
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Document
- RCC sheet and bar bending schedule (the list of every steel bar)
- In de ERP
- Bill of Quantities
Concrete and the estimate
Opdracht 4 · 35 min
Prijzenboekposten met de kostenindex, geanalyseerde posten zonder
- U levert
- The estimate total, Direct Cost
- Document
- Schedule base rates and the station cost index
- In de ERP
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.