Introduksjon til kurset · 3 min
Enhetsprisanalyse etter CPWD-praksis (India)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Fiktivt prosjekt- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- Arbeid i ERP
- 4 oppgaver, omtrent 2 t 20 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersOppgave 1
- RCC M25 sheet and bar bending scheduleOppgave 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote BOppgave 2
Går fra deg
- Brickwork rate per m³Oppgave 1
- Complete rate and the gap to quote AOppgave 2
- RCC rate and the reinforcement lineOppgave 3
- Estimate totalOppgave 4
Din vei gjennom prosjektet
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
Oppgave 1 · 35 min
Murverk: den rimeligste kilden, deretter kostnaden per m3
- Du leverer
- Cost of 10 m³ of brickwork from the cheaper brick source
- Dokument
- Analysis sheet and two brick offers
- I ERP
- Bill of Quantities
Analyse the work
Oppgave 2 · 30 min
To entreprenørtilbud mot CPWD-prisen
- Du leverer
- The CPWD rate on line 2.1, and how far quote A sits below it
- Dokument
- Two contractor quotes
- I ERP
- Bill of Quantities
Concrete and the estimate
Oppgave 3 · 40 min
RCC M25: hva som hører hjemme i betongenhetsprisen
- Du leverer
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Dokument
- RCC sheet and bar bending schedule (the list of every steel bar)
- I ERP
- Bill of Quantities
Concrete and the estimate
Oppgave 4 · 35 min
Poster i prisboken med kostnadsindeks, analyserte poster uten
- Du leverer
- The estimate total, Direct Cost
- Dokument
- Schedule base rates and the station cost index
- I ERP
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.