Introduktion till kursen · 3 min

À-prisanalys enligt CPWD-praxis (Indien)

You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.

Starta uppgift 1

A single-storey health centre in grey block with bamboo scaffolding on red earth, a concrete mixer, cement bags and a stack of blocks in front, two workers in orange vests walking by.Fiktivt projekt
Kesarwadi Primary Health CentreVillage health centre · walls and frame rising
Building
Single-storey primary health centre in a village
Contract
Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
Currency
Rupees, worked before GST
Arbete i ERP
4 uppgifter, cirka 2 h 20 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Site engineerSends the analysis sheets
    • Brickwork analysis sheet and two brick offersUppgift 1
    • RCC M25 sheet and bar bending scheduleUppgift 3
  • Two contractorsQuote line 2.1 their own way
    • Quote A and quote BUppgift 2
DuEstimating engineer, detailed estimate

Går från dig

    • Brickwork rate per m³Uppgift 1
    • Complete rate and the gap to quote AUppgift 2
    • RCC rate and the reinforcement lineUppgift 3
    • Estimate totalUppgift 4
    Executive EngineerChecks your rates

Din väg genom projektet

Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.

  1. Analyse the work

    Uppgift 1 · 35 min

    Tegelmurverk: det billigare alternativet, därefter kostnaden per m3

    Du tar fram
    Cost of 10 m³ of brickwork from the cheaper brick source
    Dokument
    Analysis sheet and two brick offers
    I ERP
    Bill of Quantities
  2. Analyse the work

    Uppgift 2 · 30 min

    Två entreprenörsanbud mot CPWD-priset

    Du tar fram
    The CPWD rate on line 2.1, and how far quote A sits below it
    Dokument
    Two contractor quotes
    I ERP
    Bill of Quantities
  3. Concrete and the estimate

    Uppgift 3 · 40 min

    RCC M25: vad som ingår i betongens A-pris

    Du tar fram
    RCC M25 rate on line 2.2, reinforcement kept on line 1.3
    Dokument
    RCC sheet and bar bending schedule (the list of every steel bar)
    I ERP
    Bill of Quantities
  4. Concrete and the estimate

    Uppgift 4 · 35 min

    Prislistans poster med kostnadsindex, analyserade poster utan

    Du tar fram
    The estimate total, Direct Cost
    Dokument
    Schedule base rates and the station cost index
    I ERP
    Bill of Quantities

From an analysis sheet to an estimate

A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.

Mason, beldar, bhistiCarriage to siteMaterials
Uppgift 1What the work consumesPer 10 m³: materials, carriage from the source to site, and labour at the day rates of the schedule. The cheaper source counts delivered, not at the gate.
Profit and overheadsWater chargesMason, beldar, bhistiCarriage to siteMaterials
Uppgift 2Water, then profit and overheadsWater charges go on the cost first. The percentage for profit and overheads then goes on that sum, not on labour alone and not in one step.
Bars, paid on line 1.3Labour and mixerCement, sand, aggregate
Uppgift 3What belongs in the concrete rateThe sheet lists the bars, but line 1.3 already pays reinforcement by weight. Leave them in the rate and they are paid twice.
Analysed items, no indexCost indexSchedule base rates
Uppgift 4Index on schedule items onlySchedule items take base rate plus the station cost index. Rates analysed from market rates are already at site prices and take none.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.