Introduktion till kursen · 3 min
À-prisanalys enligt CPWD-praxis (Indien)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Fiktivt projekt- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- Arbete i ERP
- 4 uppgifter, cirka 2 h 20 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersUppgift 1
- RCC M25 sheet and bar bending scheduleUppgift 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote BUppgift 2
Går från dig
- Brickwork rate per m³Uppgift 1
- Complete rate and the gap to quote AUppgift 2
- RCC rate and the reinforcement lineUppgift 3
- Estimate totalUppgift 4
Din väg genom projektet
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
Uppgift 1 · 35 min
Tegelmurverk: det billigare alternativet, därefter kostnaden per m3
- Du tar fram
- Cost of 10 m³ of brickwork from the cheaper brick source
- Dokument
- Analysis sheet and two brick offers
- I ERP
- Bill of Quantities
Analyse the work
Uppgift 2 · 30 min
Två entreprenörsanbud mot CPWD-priset
- Du tar fram
- The CPWD rate on line 2.1, and how far quote A sits below it
- Dokument
- Two contractor quotes
- I ERP
- Bill of Quantities
Concrete and the estimate
Uppgift 3 · 40 min
RCC M25: vad som ingår i betongens A-pris
- Du tar fram
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Dokument
- RCC sheet and bar bending schedule (the list of every steel bar)
- I ERP
- Bill of Quantities
Concrete and the estimate
Uppgift 4 · 35 min
Prislistans poster med kostnadsindex, analyserade poster utan
- Du tar fram
- The estimate total, Direct Cost
- Dokument
- Schedule base rates and the station cost index
- I ERP
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.