Rate analysis ayon sa kasanayan ng CPWD (India)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Kathang-isip na proyekto- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- Trabaho sa ERP
- 4 gawain, mga 2 oras 20 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersGawain 1
- RCC M25 sheet and bar bending scheduleGawain 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote BGawain 2
Lumalabas sa iyo
- Brickwork rate per m³Gawain 1
- Complete rate and the gap to quote AGawain 2
- RCC rate and the reinforcement lineGawain 3
- Estimate totalGawain 4
Ang ruta mo sa proyekto
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
Gawain 1 · 35 min
Trabahong Ladrillo: ang mas murang supplier, pagkatapos ay ang halaga bawat m3
- Ang gagawin mo
- Cost of 10 m³ of brickwork from the cheaper brick source
- Dokumento
- Analysis sheet and two brick offers
- Sa ERP
- Bill of Quantities
Analyse the work
Gawain 2 · 30 min
Dalawang quote ng kontraktor laban sa rate ng CPWD
- Ang gagawin mo
- The CPWD rate on line 2.1, and how far quote A sits below it
- Dokumento
- Two contractor quotes
- Sa ERP
- Bill of Quantities
Concrete and the estimate
Gawain 3 · 40 min
RCC M25: ano ang dapat kasama sa presyo ng konkreto
- Ang gagawin mo
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Dokumento
- RCC sheet and bar bending schedule (the list of every steel bar)
- Sa ERP
- Bill of Quantities
Concrete and the estimate
Gawain 4 · 35 min
Mga item ng schedule na may cost index, mga sinuring item na wala
- Ang gagawin mo
- The estimate total, Direct Cost
- Dokumento
- Schedule base rates and the station cost index
- Sa ERP
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.