Сургалтын танилцуулга · 3 мин
CPWD-ийн практикаар үнийн шинжилгээ (Энэтхэг)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Зохиомол төсөл- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- ERP дээрх ажил
- Даалгавар: 4, ойролцоогоор 2 цаг 20 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersДаалгавар 1
- RCC M25 sheet and bar bending scheduleДаалгавар 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote BДаалгавар 2
Танаас гардаг
- Brickwork rate per m³Даалгавар 1
- Complete rate and the gap to quote AДаалгавар 2
- RCC rate and the reinforcement lineДаалгавар 3
- Estimate totalДаалгавар 4
Төслөөр явах таны зам
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
Даалгавар 1 · 35 мин
Тоосгон өрлөг: илүү хямд эх үүсвэр, дараа нь 1 m3-ийн өртөг
- Үр дүн
- Cost of 10 m³ of brickwork from the cheaper brick source
- Баримт бичиг
- Analysis sheet and two brick offers
- ERP дээр
- Bill of Quantities
Analyse the work
Даалгавар 2 · 30 мин
CPWD нэгж үнэтэй харьцуулсан гүйцэтгэгчийн хоёр үнийн санал
- Үр дүн
- The CPWD rate on line 2.1, and how far quote A sits below it
- Баримт бичиг
- Two contractor quotes
- ERP дээр
- Bill of Quantities
Concrete and the estimate
Даалгавар 3 · 40 мин
RCC M25: бетоны нэгж үнэд юу орох вэ
- Үр дүн
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Баримт бичиг
- RCC sheet and bar bending schedule (the list of every steel bar)
- ERP дээр
- Bill of Quantities
Concrete and the estimate
Даалгавар 4 · 35 мин
Жагсаалтын байлууд өртгийн индекстэй, шинжилсэн байлууд индексгүй
- Үр дүн
- The estimate total, Direct Cost
- Баримт бичиг
- Schedule base rates and the station cost index
- ERP дээр
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.