OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

Сургалтын танилцуулга · 3 мин

CPWD-ийн практикаар үнийн шинжилгээ (Энэтхэг)

You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.

1-р даалгаврыг эхлэх

A single-storey health centre in grey block with bamboo scaffolding on red earth, a concrete mixer, cement bags and a stack of blocks in front, two workers in orange vests walking by.Зохиомол төсөл
Kesarwadi Primary Health CentreVillage health centre · walls and frame rising
Building
Single-storey primary health centre in a village
Contract
Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
Currency
Rupees, worked before GST
ERP дээрх ажил
Даалгавар: 4, ойролцоогоор 2 цаг 20 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • Site engineerSends the analysis sheets
    • Brickwork analysis sheet and two brick offersДаалгавар 1
    • RCC M25 sheet and bar bending scheduleДаалгавар 3
  • Two contractorsQuote line 2.1 their own way
    • Quote A and quote BДаалгавар 2
ТаEstimating engineer, detailed estimate

Танаас гардаг

    • Brickwork rate per m³Даалгавар 1
    • Complete rate and the gap to quote AДаалгавар 2
    • RCC rate and the reinforcement lineДаалгавар 3
    • Estimate totalДаалгавар 4
    Executive EngineerChecks your rates

Төслөөр явах таны зам

Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.

  1. Analyse the work

    Даалгавар 1 · 35 мин

    Тоосгон өрлөг: илүү хямд эх үүсвэр, дараа нь 1 m3-ийн өртөг

    Үр дүн
    Cost of 10 m³ of brickwork from the cheaper brick source
    Баримт бичиг
    Analysis sheet and two brick offers
    ERP дээр
    Bill of Quantities
  2. Analyse the work

    Даалгавар 2 · 30 мин

    CPWD нэгж үнэтэй харьцуулсан гүйцэтгэгчийн хоёр үнийн санал

    Үр дүн
    The CPWD rate on line 2.1, and how far quote A sits below it
    Баримт бичиг
    Two contractor quotes
    ERP дээр
    Bill of Quantities
  3. Concrete and the estimate

    Даалгавар 3 · 40 мин

    RCC M25: бетоны нэгж үнэд юу орох вэ

    Үр дүн
    RCC M25 rate on line 2.2, reinforcement kept on line 1.3
    Баримт бичиг
    RCC sheet and bar bending schedule (the list of every steel bar)
    ERP дээр
    Bill of Quantities
  4. Concrete and the estimate

    Даалгавар 4 · 35 мин

    Жагсаалтын байлууд өртгийн индекстэй, шинжилсэн байлууд индексгүй

    Үр дүн
    The estimate total, Direct Cost
    Баримт бичиг
    Schedule base rates and the station cost index
    ERP дээр
    Bill of Quantities

From an analysis sheet to an estimate

A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.

Mason, beldar, bhistiCarriage to siteMaterials
Даалгавар 1What the work consumesPer 10 m³: materials, carriage from the source to site, and labour at the day rates of the schedule. The cheaper source counts delivered, not at the gate.
Profit and overheadsWater chargesMason, beldar, bhistiCarriage to siteMaterials
Даалгавар 2Water, then profit and overheadsWater charges go on the cost first. The percentage for profit and overheads then goes on that sum, not on labour alone and not in one step.
Bars, paid on line 1.3Labour and mixerCement, sand, aggregate
Даалгавар 3What belongs in the concrete rateThe sheet lists the bars, but line 1.3 already pays reinforcement by weight. Leave them in the rate and they are paid twice.
Analysed items, no indexCost indexSchedule base rates
Даалгавар 4Index on schedule items onlySchedule items take base rate plus the station cost index. Rates analysed from market rates are already at site prices and take none.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.