OpenConstruction Academy
Sign in / Register
EN

Course introduction · 3 min

Rate analysis to CPWD practice (India)

You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.

Start task 1

A single-storey health centre in grey block with bamboo scaffolding on red earth, a concrete mixer, cement bags and a stack of blocks in front, two workers in orange vests walking by.Fictional project
Kesarwadi Primary Health CentreVillage health centre · walls and frame rising
Building
Single-storey primary health centre in a village
Contract
Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
Currency
Rupees, worked before GST
Work in the ERP
4 tasks, about 2 h 20 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Site engineerSends the analysis sheets
    • Brickwork analysis sheet and two brick offersTask 1
    • RCC M25 sheet and bar bending scheduleTask 3
  • Two contractorsQuote line 2.1 their own way
    • Quote A and quote BTask 2
YouEstimating engineer, detailed estimate

Goes from you

    • Brickwork rate per m³Task 1
    • Complete rate and the gap to quote ATask 2
    • RCC rate and the reinforcement lineTask 3
    • Estimate totalTask 4
    Executive EngineerChecks your rates

Your route through the job

Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.

  1. Analyse the work

    Task 1 · 35 min

    Brickwork: the cheaper source, then the cost per m3

    You produce
    Cost of 10 m³ of brickwork from the cheaper brick source
    Document
    Analysis sheet and two brick offers
    In the ERP
    Bill of Quantities
  2. Analyse the work

    Task 2 · 30 min

    Two contractor quotes against the CPWD rate

    You produce
    The CPWD rate on line 2.1, and how far quote A sits below it
    Document
    Two contractor quotes
    In the ERP
    Bill of Quantities
  3. Concrete and the estimate

    Task 3 · 40 min

    RCC M25: what belongs in the concrete rate

    You produce
    RCC M25 rate on line 2.2, reinforcement kept on line 1.3
    Document
    RCC sheet and bar bending schedule (the list of every steel bar)
    In the ERP
    Bill of Quantities
  4. Concrete and the estimate

    Task 4 · 35 min

    Schedule items with the cost index, analysed items without

    You produce
    The estimate total, Direct Cost
    Document
    Schedule base rates and the station cost index
    In the ERP
    Bill of Quantities

From an analysis sheet to an estimate

A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.

Mason, beldar, bhistiCarriage to siteMaterials
Task 1What the work consumesPer 10 m³: materials, carriage from the source to site, and labour at the day rates of the schedule. The cheaper source counts delivered, not at the gate.
Profit and overheadsWater chargesMason, beldar, bhistiCarriage to siteMaterials
Task 2Water, then profit and overheadsWater charges go on the cost first. The percentage for profit and overheads then goes on that sum, not on labour alone and not in one step.
Bars, paid on line 1.3Labour and mixerCement, sand, aggregate
Task 3What belongs in the concrete rateThe sheet lists the bars, but line 1.3 already pays reinforcement by weight. Leave them in the rate and they are paid twice.
Analysed items, no indexCost indexSchedule base rates
Task 4Index on schedule items onlySchedule items take base rate plus the station cost index. Rates analysed from market rates are already at site prices and take none.

Blue is what the task adds; grey is carried over from before.

In short. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.