OpenConstruction Academy
Кирүү / Катталуу
KY

Курска киришүү · 3 мүн

CPWD практикасы боюнча баа талдоосу (Индия)

You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.

1-тапшырманы баштоо

A single-storey health centre in grey block with bamboo scaffolding on red earth, a concrete mixer, cement bags and a stack of blocks in front, two workers in orange vests walking by.Ойдон чыгарылган долбоор
Kesarwadi Primary Health CentreVillage health centre · walls and frame rising
Building
Single-storey primary health centre in a village
Contract
Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
Currency
Rupees, worked before GST
ERPдеги иш
Тапшырмалар: 4, болжол менен 2 саат 20 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Site engineerSends the analysis sheets
    • Brickwork analysis sheet and two brick offers1-тапшырма
    • RCC M25 sheet and bar bending schedule3-тапшырма
  • Two contractorsQuote line 2.1 their own way
    • Quote A and quote B2-тапшырма
СизEstimating engineer, detailed estimate

Сизден кетет

    • Brickwork rate per m³1-тапшырма
    • Complete rate and the gap to quote A2-тапшырма
    • RCC rate and the reinforcement line3-тапшырма
    • Estimate total4-тапшырма
    Executive EngineerChecks your rates

Долбоор боюнча жолуңуз

Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.

  1. Analyse the work

    1-тапшырма · 35 мүн

    Кирпич каландысы: арзаныраак булак, андан соң m3 үчүн наркы

    Натыйжа
    Cost of 10 m³ of brickwork from the cheaper brick source
    Документ
    Analysis sheet and two brick offers
    ERPде
    Bill of Quantities
  2. Analyse the work

    2-тапшырма · 30 мүн

    CPWD баасына каршы эки подрядчынын сунушу

    Натыйжа
    The CPWD rate on line 2.1, and how far quote A sits below it
    Документ
    Two contractor quotes
    ERPде
    Bill of Quantities
  3. Concrete and the estimate

    3-тапшырма · 40 мүн

    RCC M25: бетон наркына эмне кирет

    Натыйжа
    RCC M25 rate on line 2.2, reinforcement kept on line 1.3
    Документ
    RCC sheet and bar bending schedule (the list of every steel bar)
    ERPде
    Bill of Quantities
  4. Concrete and the estimate

    4-тапшырма · 35 мүн

    Баалар тизмесиндеги позициялар баа индекси менен, талданган позициялар индекссиз

    Натыйжа
    The estimate total, Direct Cost
    Документ
    Schedule base rates and the station cost index
    ERPде
    Bill of Quantities

From an analysis sheet to an estimate

A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.

Mason, beldar, bhistiCarriage to siteMaterials
1-тапшырмаWhat the work consumesPer 10 m³: materials, carriage from the source to site, and labour at the day rates of the schedule. The cheaper source counts delivered, not at the gate.
Profit and overheadsWater chargesMason, beldar, bhistiCarriage to siteMaterials
2-тапшырмаWater, then profit and overheadsWater charges go on the cost first. The percentage for profit and overheads then goes on that sum, not on labour alone and not in one step.
Bars, paid on line 1.3Labour and mixerCement, sand, aggregate
3-тапшырмаWhat belongs in the concrete rateThe sheet lists the bars, but line 1.3 already pays reinforcement by weight. Leave them in the rate and they are paid twice.
Analysed items, no indexCost indexSchedule base rates
4-тапшырмаIndex on schedule items onlySchedule items take base rate plus the station cost index. Rates analysed from market rates are already at site prices and take none.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.