Курска киришүү · 3 мүн
CPWD практикасы боюнча баа талдоосу (Индия)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Ойдон чыгарылган долбоор- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- ERPдеги иш
- Тапшырмалар: 4, болжол менен 2 саат 20 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offers1-тапшырма
- RCC M25 sheet and bar bending schedule3-тапшырма
- Two contractorsQuote line 2.1 their own way
- Quote A and quote B2-тапшырма
Сизден кетет
- Brickwork rate per m³1-тапшырма
- Complete rate and the gap to quote A2-тапшырма
- RCC rate and the reinforcement line3-тапшырма
- Estimate total4-тапшырма
Долбоор боюнча жолуңуз
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
1-тапшырма · 35 мүн
Кирпич каландысы: арзаныраак булак, андан соң m3 үчүн наркы
- Натыйжа
- Cost of 10 m³ of brickwork from the cheaper brick source
- Документ
- Analysis sheet and two brick offers
- ERPде
- Bill of Quantities
Analyse the work
2-тапшырма · 30 мүн
CPWD баасына каршы эки подрядчынын сунушу
- Натыйжа
- The CPWD rate on line 2.1, and how far quote A sits below it
- Документ
- Two contractor quotes
- ERPде
- Bill of Quantities
Concrete and the estimate
3-тапшырма · 40 мүн
RCC M25: бетон наркына эмне кирет
- Натыйжа
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Документ
- RCC sheet and bar bending schedule (the list of every steel bar)
- ERPде
- Bill of Quantities
Concrete and the estimate
4-тапшырма · 35 мүн
Баалар тизмесиндеги позициялар баа индекси менен, талданган позициялар индекссиз
- Натыйжа
- The estimate total, Direct Cost
- Документ
- Schedule base rates and the station cost index
- ERPде
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.