Uvod u tečaj · 3 min
Analiza cijene prema praksi CPWD-a (Indija)
You are the estimating engineer for a district council: you prepare the detailed estimate, the priced list of all work, for a primary health centre before it goes to tender. In four tasks you build the rates for brickwork and reinforced concrete (RCC) from analysis sheets, the method of India's Central Public Works Department (CPWD), then price the whole estimate.
Izmišljeni projekt- Building
- Single-storey primary health centre in a village
- Contract
- Public works contract, priced from the schedule of rates (the government's published rates) with a station cost index, the percentage for this location
- Currency
- Rupees, worked before GST
- Rad u ERP-u
- Zadataka: 4, oko 2 h 20 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Site engineerSends the analysis sheets
- Brickwork analysis sheet and two brick offersZadatak 1
- RCC M25 sheet and bar bending scheduleZadatak 3
- Two contractorsQuote line 2.1 their own way
- Quote A and quote BZadatak 2
Odlazi od vas
- Brickwork rate per m³Zadatak 1
- Complete rate and the gap to quote AZadatak 2
- RCC rate and the reinforcement lineZadatak 3
- Estimate totalZadatak 4
Vaš put kroz projekt
Three tasks to build a rate, one to price the estimate. Brickwork comes first because the two later steps reuse its logic. Start with task 1: in the Bill of Quantities you cost 10 m³ of brickwork from the cheaper brick source.
Analyse the work
Zadatak 1 · 35 min
Zidanje opekom: povoljniji izvor, zatim trošak po m3
- Vaš rezultat
- Cost of 10 m³ of brickwork from the cheaper brick source
- Dokument
- Analysis sheet and two brick offers
- U ERP-u
- Bill of Quantities
Analyse the work
Zadatak 2 · 30 min
Dvije ponude izvođača prema CPWD cijeni
- Vaš rezultat
- The CPWD rate on line 2.1, and how far quote A sits below it
- Dokument
- Two contractor quotes
- U ERP-u
- Bill of Quantities
Concrete and the estimate
Zadatak 3 · 40 min
RCC M25: što ulazi u jediničnu cijenu betona
- Vaš rezultat
- RCC M25 rate on line 2.2, reinforcement kept on line 1.3
- Dokument
- RCC sheet and bar bending schedule (the list of every steel bar)
- U ERP-u
- Bill of Quantities
Concrete and the estimate
Zadatak 4 · 35 min
Stavke cjenika s indeksom troškova, analizirane stavke bez njega
- Vaš rezultat
- The estimate total, Direct Cost
- Dokument
- Schedule base rates and the station cost index
- U ERP-u
- Bill of Quantities
From an analysis sheet to an estimate
A rate is built in layers, and each layer has one place to go. Task 4 shows which rates take the cost index and which do not.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Price the cheaper source delivered. Water first, then profit and overheads on the sum. Pay steel once. Index the schedule, not the analysis.