Θεωρία πριν από την εργασία 4 · 9 λ.
Valuing work done: gross, retention, net, VAT
Ενδιάμεση Αποτίμηση 1 (Σεπτέμβριος)
Μετά από αυτή τη διάλεξη μπορείτε να
- Value work done as a percentage of each schedule line and add up the gross valuation.
- Apply retention to the gross using the percentage the contract states, and find the net due.
- Say what VAT is charged on, and why.
What a valuation sees on site
A valuation is a walk round the site with a schedule in your hand. Tap each point to see what it becomes on paper.

The foundations are complete and accepted. The work is properly executed, so the full value of that schedule line is due.
Πού βρίσκεται στην εκτίμησή σαςA schedule line at 100 per cent: its whole value goes into the gross valuation.The frame is part built. You value the share that is properly executed, judged on site, not the share of the time that has gone by.
Πού βρίσκεται στην εκτίμησή σαςA schedule line at a percentage: schedule value × percent complete.Nothing is built here, however soon it will be. Work that has not been done is not valued.
Πού βρίσκεται στην εκτίμησή σαςA schedule line at 0 per cent contributes nothing to the gross.Steel and bricks are delivered but not yet built in. Whether they can be valued depends on the contract, and usually on how they are stored and protected.
Πού βρίσκεται στην εκτίμησή σαςA separate line, only where the contract allows it. Read the contract before adding it.The cabins and site team are there every week. Preliminaries are valued with time, not with the amount of concrete poured.
Πού βρίσκεται στην εκτίμησή σαςThe preliminaries line, at the percentage of the programme that has elapsed.
One interim valuation, start to finish
Different numbers from your task, same steps. The contract holds retention at 4% in this example.
- Substructure £120,000 at 60% complete. Frame £200,000 at 15%. Preliminaries £50,000 at 10%.
- Retention 4% of the gross valuation. VAT 20%.
- This is the first valuation: nothing has been certified before.
- 1 Substructure
- 2 Frame
- 3 Preliminaries
- 4 Gross
- 1 Substructure
- 2 Frame
- 3 Preliminaries
- 4 Gross
Value each line
Add the value of the three lines: each is its schedule value times its percentage. What is the gross valuation?
Υπόδειξη: Three products, then one sum.
- 1 Gross
- 2 Retention
- 1 Gross
- 2 Retention
Hold retention
Retention is a percentage of the gross valuation. How much is held back?
Υπόδειξη: Take the percentage of the gross, not of any single line.
- 1 Gross
- 2 Retention
- 3 Net due
- 1 Gross
- 2 Retention
- 3 Net due
Net due
Gross valuation less retention. What is the net due, before VAT?
Υπόδειξη: Subtract step 2 from step 1.
- 1 Net due
- 2 VAT
- 3 Invoice
- 1 Net due
- 2 VAT
- 3 Invoice
VAT on the payment
VAT follows the payment that is made or invoiced. What is VAT on the net due?
Υπόδειξη: Apply the VAT percentage to the net due.
Ελέγξτε τον εαυτό σας
At the second valuation the gross valuation to date is £260,000. Retention is 4%. The first valuation certified a net of £102,720. What is the net due now, before VAT?
The software's contract form suggests a retention percentage, but the contract itself says otherwise. Which one do you apply?
A default is a starting value, not a term of the contract.
The contract is the authority. If the form shows another figure, change the form.
Retention is a contractual percentage, not a negotiation.