OpenConstruction Academy
Logga in / Registrera
SV

Teori före uppgift 4 · 9 min

Valuing work done: gross, retention, net, VAT

Interimsvärdering 1 (september)

Efter den här lektionen kan du

  1. Value work done as a percentage of each schedule line and add up the gross valuation.
  2. Apply retention to the gross using the percentage the contract states, and find the net due.
  3. Say what VAT is charged on, and why.

What a valuation sees on site

A valuation is a walk round the site with a schedule in your hand. Tap each point to see what it becomes on paper.

A construction site mid-project: finished foundations on the left, a half-built concrete frame in the centre, an empty cleared plot on the right, steel bars and bricks in the foreground, site cabins behind.
  1. The foundations are complete and accepted. The work is properly executed, so the full value of that schedule line is due.

    Var den finns i din kalkylA schedule line at 100 per cent: its whole value goes into the gross valuation.
  2. The frame is part built. You value the share that is properly executed, judged on site, not the share of the time that has gone by.

    Var den finns i din kalkylA schedule line at a percentage: schedule value × percent complete.
  3. Nothing is built here, however soon it will be. Work that has not been done is not valued.

    Var den finns i din kalkylA schedule line at 0 per cent contributes nothing to the gross.
  4. Steel and bricks are delivered but not yet built in. Whether they can be valued depends on the contract, and usually on how they are stored and protected.

    Var den finns i din kalkylA separate line, only where the contract allows it. Read the contract before adding it.
  5. The cabins and site team are there every week. Preliminaries are valued with time, not with the amount of concrete poured.

    Var den finns i din kalkylThe preliminaries line, at the percentage of the programme that has elapsed.

One interim valuation, start to finish

Different numbers from your task, same steps. The contract holds retention at 4% in this example.

Inte skalenlig
Uppgiften
  • Substructure £120,000 at 60% complete. Frame £200,000 at 15%. Preliminaries £50,000 at 10%.
  • Retention 4% of the gross valuation. VAT 20%.
  • This is the first valuation: nothing has been certified before.
?1?2?3?4
  • 1 Substructure
  • 2 Frame
  • 3 Preliminaries
  • 4 Gross
+£72,0001+£30,0002+£5,0003£107,0004
  • 1 Substructure
  • 2 Frame
  • 3 Preliminaries
  • 4 Gross
Steg 1 av 4

Value each line

Add the value of the three lines: each is its schedule value times its percentage. What is the gross valuation?

Substructure £72,000, frame £30,000, preliminaries £5,000. Gross valuation £107,000.

£107,0001?2
  • 1 Gross
  • 2 Retention
£107,0001−£4,2802
  • 1 Gross
  • 2 Retention
Steg 2 av 4

Hold retention

Retention is a percentage of the gross valuation. How much is held back?

4% of £107,000 = £4,280. The client holds this as security for defects, and releases it later.

£107,0001−£4,2802?3
  • 1 Gross
  • 2 Retention
  • 3 Net due
£107,0001−£4,2802£102,7203
  • 1 Gross
  • 2 Retention
  • 3 Net due
Steg 3 av 4

Net due

Gross valuation less retention. What is the net due, before VAT?

£107,000 − £4,280 = £102,720. For a later valuation you would also deduct what earlier certificates already paid.

£102,7201?2?3
  • 1 Net due
  • 2 VAT
  • 3 Invoice
£102,7201+£20,5442£123,2643
  • 1 Net due
  • 2 VAT
  • 3 Invoice
Steg 4 av 4

VAT on the payment

VAT follows the payment that is made or invoiced. What is VAT on the net due?

20% of £102,720 = £20,544. The retained part carries its VAT later, when it is paid out. The invoice is £102,720 plus £20,544.

Kort sagt. Line values add to a gross. Retention comes off the gross. VAT is worked on the payment that remains.

Testa dig själv

Fråga 1 av 3

At the second valuation the gross valuation to date is £260,000. Retention is 4%. The first valuation certified a net of £102,720. What is the net due now, before VAT?

Gross to date 260,000. Retention to date 4% = 10,400. Net to date 249,600. Less the 102,720 already certified: £146,880.
Fråga 2 av 3

The software's contract form suggests a retention percentage, but the contract itself says otherwise. Which one do you apply?

  • A default is a starting value, not a term of the contract.

  • The contract is the authority. If the form shows another figure, change the form.

  • Retention is a contractual percentage, not a negotiation.

Fråga 3 av 3

The gross valuation is £100,000 and retention is 5%. VAT is 20%, worked on the payment. What is the VAT?

Net due 95,000. VAT 20% = £19,000. The VAT on the retained 5,000 comes with its release.